ONSHORE WIND Β· MISO

Onshore wind project MPC02900, Barnes County

Onshore wind project MPC02900, Barnes County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Barnes County, North Dakota, connecting to Minnkota Power Cooperative.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
MPC02900
Grid region
MISO (Midcontinent)
Utility / transmission owner
Minnkota Power Cooperative
Connection point (POI)
Jamestown - Buffalo 345 kV Line
Location
Barnes County, North Dakota
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
21 July 2016
Proposed online date
December 2018

Location

Marker shows the centre of Barnes County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Barnes County