Onshore wind project G598, Adams County

Onshore wind project G598, Adams County is a 144 MW onshore wind request withdrawn in the MISO interconnection queue, in Adams County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2006 (completed)
  2. Withdrawn / abandonedApr 2013 (project stopped here)
  3. ConsentedApr 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G598
Grid region
MISO (Midcontinent)
Connection point (POI)
120 kV sub at E. Quincy-Clayton-Meredosia 115-138 kV line
Location
Adams County, Illinois
Technology
Wind: 144 MW
Total requested
144 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
15 February 2006
Agreement signed
1 April 2011
Proposed online date
May 2006
Withdrawn
April 2013

Location

Marker shows the centre of Adams County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Adams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem