ONSHORE WIND Β· MISO

Onshore wind project G339, Dickey County

Onshore wind project G339, Dickey County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Dickey County, North Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2003 (completed)
  2. Withdrawn / abandonedOct 2003 (project stopped here)
  3. ConsentedOct 2003 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G339
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Dickey County, North Dakota
Technology
Wind: 150 MW
Total requested
150 MW
Queue status
Withdrawn
Entered queue
2 May 2003
Agreement signed
7 October 2003
Proposed online date
July 2003
Withdrawn
October 2003

Location

Marker shows the centre of Dickey County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Dickey County