United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

SOLAR Β· MISO

Solar project J647, Muskegon County

Solar project J647, Muskegon County is a 147 MW solar request withdrawn in the MISO interconnection queue, in Muskegon County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2016 (completed)
  2. Withdrawn / abandonedSep 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J647
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
BC Cobb - Four Mile 138kV Line
Location
Muskegon County, Michigan
Technology
Solar: 147 MW
Total requested
147 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
20 June 2016
Proposed online date
September 2021
Withdrawn
September 2018

Location

Marker shows the centre of Muskegon County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Muskegon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem