πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

ONSHORE WIND Β· MISO

Onshore wind project J609, Muskegon County

Onshore wind project J609, Muskegon County is a 136 MW onshore wind request withdrawn in the MISO interconnection queue, in Muskegon County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedAug 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J609
Grid region
MISO (Midcontinent)
Connection point (POI)
White Road 115kV Substation
Location
Muskegon County, Michigan
Technology
Wind: 136 MW
Total requested
136 MW
Study phase
GIA
Queue status
Withdrawn
Entered queue
9 May 2016
Proposed online date
September 2018
Withdrawn
August 2017

Location

Marker shows the centre of Muskegon County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Muskegon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem