United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 317

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 317 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AF1-323, Albemarle County
Solar · Vista Energy Facility, LLC
55.0 MWWithdrawn / abandoned Albemarle, VAPJM Sep 2019target 2022
Solar project 1025, Jefferson County
Solar
55.0 MWWithdrawn / abandoned Jefferson, ORWest May 2018target 2020
Solar project 744, Lake County
Solar
55.0 MWWithdrawn / abandoned Lake, ORWest May 2016target 2018
Solar project 85, Hillsborough County
Solar
55.0 MWWithdrawn / abandoned Hillsborough, FLSoutheast Apr 2022target 2024
Gas project G336, Rice County
Gas
55.0 MWWithdrawn / abandoned Rice, MNMISO Apr 2003target 2005
Solar project 91, Polk County
Solar
55.0 MWWithdrawn / abandoned Polk, FLSoutheast Nov 2022target 2025
Solar project 90, Hillsborough County
Solar
55.0 MWWithdrawn / abandoned Hillsborough, FLSoutheast Jun 2022target 2024
Solar + storage project AE1-141, Mercer County
Solar + storage
55.0 MWWithdrawn / abandoned Mercer, PAPJM Sep 2018target 2021
Solar project 918573, Vance County
Solar · Masked
55.0 MWWithdrawn / abandoned Vance, NCSoutheast Sep 2023
Russell Biomass
Other
55.0 MWWithdrawn / abandoned Hampden, MAISO-NE Aug 2005target 2015
Solar project 167B, Richland County
Solar
55.0 MWWithdrawn / abandoned Richland, SCSoutheast Oct 2021
Oro Solar
Solar · Recurrent Energy
55.0 MWWithdrawn / abandoned ERCOT Nov 2013target 2017
Homer Hill Storage
Battery storage · Origis Development
54.7 MWWithdrawn / abandoned Cattaraugus, NYNYISO Nov 2022
Solar project 3, Hillsborough County
Solar
54.6 MWWithdrawn / abandoned Hillsborough, FLSoutheast Apr 2017target 2018
Solar project AI1-157, Mchenry County
Solar
54.4 MWWithdrawn / abandoned Mchenry, ILPJM Sep 2022target 2027
La Feria Irrigation District 1 Solar
Solar · La Patrona Floating Solar LLC
54.4 MWWithdrawn / abandoned Cameron, TXERCOT May 2023target 2027
Solar
Solar
54.4 MWWithdrawn / abandoned Grafton, NHISO-NE Oct 2022target 2024
Harlingen Irrigation District 1 Solar
Solar · Six Shooter Floating Solar LLC
54.3 MWWithdrawn / abandoned Cameron, TXERCOT May 2023target 2027
Solar project IC-631, Calhoun County
Solar
54.2 MWWithdrawn / abandoned Calhoun, FLSoutheast Apr 2017
Solar Increase (QP1145)
Solar
54.1 MWWithdrawn / abandoned Hancock, MEISO-NE Aug 2022target 2026
Solar project IC-569, Dale County
Solar
54.0 MWWithdrawn / abandoned Dale, ALSoutheast Dec 2016
Solar project GEN-2016-077, Terry County
Solar
54.0 MWWithdrawn / abandoned Terry, TXSPP Jun 2016target 2022
Solar project AG2-063, Clark County
Solar · TerraForm Twin Creeks Solar, LLC
54.0 MWWithdrawn / abandoned Clark, OHPJM Mar 2025target 2023
Gas project J1148, Posey County
Gas
54.0 MWWithdrawn / abandoned Posey, INMISO Mar 2018target 2022
Solar + storage project 20230828002, Orangeburg County
Solar + storage
54.0 MWWithdrawn / abandoned Orangeburg, SCSoutheast target 2026
Onshore wind project J952, Corson County
Onshore wind
54.0 MWWithdrawn / abandoned Corson, SDMISO Feb 2018target 2022
Solar project AF2-125, Dekalb County
Solar
54.0 MWWithdrawn / abandoned Dekalb, INPJM Feb 2020target 2023
Solar project AG1-457, Somerset County
Solar
54.0 MWWithdrawn / abandoned Somerset, PAPJM Sep 2020target 2023
Solar project AF1-267, Madison County
Solar
54.0 MWWithdrawn / abandoned Madison, KYPJM Sep 2019target 2022
Solar project AG1-530, Clark County
Solar
54.0 MWWithdrawn / abandoned Clark, OHPJM Sep 2020target 2023
Sloopy Storage
Battery storage · Invenergy Storage Development LLC
54.0 MWWithdrawn / abandoned Clark, OHPJM Sep 2021target 2025
Solar project 51, Pima County
Solar
54.0 MWWithdrawn / abandoned Pima, AZWest Oct 2016target 2018
Solar project AG2-385, Clark County
Solar · TerraForm Twin Creeks Solar, LLC
54.0 MWWithdrawn / abandoned Clark, OHPJM Mar 2025target 2023
Onshore wind project R60, Sac County
Onshore wind
54.0 MWWithdrawn / abandoned Sac, IAMISO Apr 2009target 2010
Gas project AB2-152, City Of Hopewell County
Gas
54.0 MWWithdrawn / abandoned City Of Hopewell, VAPJM Apr 2016target 2019
Battery storage project AH1-321, Miami County
Battery storage · Invenergy Storage Development LLC
54.0 MWWithdrawn / abandoned Miami, OHPJM Sep 2021target 2025
Solar + storage project 20180508001, Fairfield County
Solar + storage
54.0 MWWithdrawn / abandoned Fairfield, SCSoutheast target 2019
Solar project AG1-056, Williams County
Solar
54.0 MWWithdrawn / abandoned Williams, OHPJM Jul 2020target 2023
Solar project AG1-355, Somerset County
Solar
54.0 MWWithdrawn / abandoned Somerset, PAPJM Sep 2020target 2023
Solar + storage project CS25-06, Grant County
Solar + storage
54.0 MWWithdrawn / abandoned Grant, WAWest Apr 2025target 2031
Solar project AG1-531, Isle Of Wight County
Solar · TCE Virginia Development, LLC
54.0 MWWithdrawn / abandoned Isle Of Wight, VAPJM Sep 2020target 2023
Salt Fork Wind Expansion
Onshore wind · Southern Power Company
54.0 MWWithdrawn / abandoned ERCOT Oct 2015target 2018
Solar + storage project AG1-473, Huntingdon County
Solar + storage · North Corners Energy, LLC
53.9 MWWithdrawn / abandoned Huntingdon, PAPJM Sep 2020target 2024
Battery Storage
Battery storage
53.7 MWWithdrawn / abandoned New Haven, CTISO-NE May 2023target 2026
Battery storage project AG1-289, Orange County
Battery storage · Locust Grove Solar, LLC
53.4 MWWithdrawn / abandoned Orange, VAPJM Sep 2020target 2023
Solar project 735, Klamath County
Solar
53.4 MWWithdrawn / abandoned Klamath, ORWest Mar 2016target 2017
Solar project AE1-136, Franklin County
Solar
53.3 MWWithdrawn / abandoned Franklin, PAPJM Sep 2018target 2021
Painted Horse Storage
Battery storage · RWE Solar Development, LLC
53.2 MWWithdrawn / abandoned ERCOT Jul 2020target 2025
Solar project AE1-107, New Castle County
Solar
53.1 MWWithdrawn / abandoned New Castle, DEPJM Sep 2018target 2021
Solar plus Battery
Solar + storage
53.1 MWWithdrawn / abandoned Merrimack, NHISO-NE Oct 2021target 2025
Page 317 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)