Solar is a 54.4 MW solar request withdrawn in the ISO-NE interconnection queue, in Grafton County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2022 (completed)
  2. Withdrawn / abandonedMay 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1329
Grid region
ISO-NE (New England)
Connection point (POI)
POI: (44.321330°, -72.003124°), National Grid's PTF 230 kV bus at Comerford No. 18 station
Location
Grafton County, New Hampshire
Technology
Solar: 54.4 MW
Total requested
54.4 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
24 October 2022
Proposed online date
June 2024
Withdrawn
May 2023

Location

Marker shows the centre of Grafton County; the queue data does not give exact sites.