ONSHORE WIND · ISO-NEGroton Wind Farm
Groton Wind Farm is a 48.0 MW onshore wind request built and operating in the ISO-NE interconnection queue, in Grafton County, New Hampshire.
Request details
- Queue ID
- 345
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- PSNH Beebe River 115 kV Substation
- Location
- Grafton County, New Hampshire
- Technology
- Wind: 48.0 MW
- Total requested
- 48.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 8 September 2010
- Agreement signed
- 9 May 2012
- Proposed online date
- December 2012
Location
Marker shows the centre of Grafton County; the queue data does not give exact sites.
Power plants in New Hampshire · Transmission lines in New Hampshire
Other requests in Grafton County
- Indeck Energy AlexandriaOther · 16.5 MW · built
- Moore Station UprateHydro · 4.6 MW · built
- Comerford Unit #1Hydro · -17.0 MW · built
- SolarSolar · 150 MW · withdrawn
- Energy StorageBattery storage · 100 MW · withdrawn
- SolarSolar · 60.0 MW · withdrawn
- SolarSolar · 54.4 MW · withdrawn
- SolarSolar · 51.0 MW · withdrawn
- Spruce Ridge Wind FarmOnshore wind · 50.8 MW · withdrawn
- SolarSolar · 33.1 MW · withdrawn
- SolarSolar · 27.0 MW · withdrawn
- SolarSolar · 21.4 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem