πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Hampshire

SOLAR Β· ISO-NE

Solar

Solar is a 21.4 MW solar request withdrawn in the ISO-NE interconnection queue, in Grafton County, New Hampshire.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2022 (completed)
  2. Withdrawn / abandonedApr 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1328
Grid region
ISO-NE (New England)
Connection point (POI)
44.336047°, -71.874785°, National Grid 230 kV Substation
Location
Grafton County, New Hampshire
Technology
Solar: 21.4 MW
Total requested
21.4 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
24 October 2022
Proposed online date
June 2024
Withdrawn
April 2023

Location

Marker shows the centre of Grafton County; the queue data does not give exact sites.

Power plants in New Hampshire Β· Transmission lines in New Hampshire

Other requests in Grafton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem