BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 53.7 MW battery storage request withdrawn in the ISO-NE interconnection queue, in New Haven County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2023 (completed)
  2. Withdrawn / abandonedSep 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1392
Grid region
ISO-NE (New England)
Connection point (POI)
Latitude: 41.492036°, Longitude: -72.762080° -Owner: Connecticut Light and Power Company, Voltage 115 kV, Substation Name: North Wallingford 115 kV Station.
Location
New Haven County, Connecticut
Technology
Battery: 53.7 MW
Total requested
53.7 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
3 May 2023
Proposed online date
September 2026
Withdrawn
September 2025

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in New Haven County