Salt Fork Wind Expansion

Salt Fork Wind Expansion is a 54.0 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2015 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedJun 2016 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
16INR0121
Grid region
ERCOT (Texas)
Developer
Southern Power Company
Connection point (POI)
79000 Gray 345kV
Technology
Wind: 54.0 MW
Total requested
54.0 MW
Study phase
IA and FIS Pending
Queue status
Withdrawn
Entered queue
28 October 2015
Agreement signed
28 June 2016
Proposed online date
December 2018

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem