United States βΊ Grid βΊ Interconnection queues βΊ Ohio
SOLAR Β· PJMSolar project AG1-530, Clark County
Solar project AG1-530, Clark County is a 54.0 MW solar request withdrawn in the PJM interconnection queue, in Clark County, Ohio, connecting to ATSI.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedOct 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-530
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Location
- Clark County, Ohio
- Technology
- Solar: 54.0 MW
- Total requested
- 54.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 30 September 2020
- Proposed online date
- December 2023
- Withdrawn
- October 2020
Location
Marker shows the centre of Clark County; the queue data does not give exact sites.
Other requests in Clark County
- Sloopy Solar Energy CenterSolar Β· 180 MW Β· agreement signed
- Solar project AG2-063, Clark CountySolar Β· 54.0 MW Β· withdrawn
- Sloopy StorageBattery storage Β· 54.0 MW Β· withdrawn
- Solar project AG2-385, Clark CountySolar Β· 54.0 MW Β· withdrawn
- Solar project AG2-378, Clark CountySolar Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem