BATTERY STORAGE Β· PJM

Sloopy Storage

Sloopy Storage is a 54.0 MW battery storage request withdrawn in the PJM interconnection queue, in Clark County, Ohio, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-319
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Developer
Invenergy Storage Development LLC
Connection point (POI)
East Springfield-London 138 kV II
Location
Clark County, Ohio
Technology
Battery: 54.0 MW
Total requested
54.0 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
10 September 2021
Proposed online date
December 2025
Withdrawn
July 2025

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Clark County