Russell Biomass

Russell Biomass is a 55.0 MW other request withdrawn in the ISO-NE interconnection queue, in Hampden County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2005 (completed)
  2. Withdrawn / abandonedMar 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
135
Grid region
ISO-NE (New England)
Connection point (POI)
Blanford - Southwick - Elm 115 kV line
Location
Hampden County, Massachusetts
Technology
Other: 55.0 MW
Total requested
55.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
19 August 2005
Proposed online date
August 2015
Withdrawn
March 2012

Location

Marker shows the centre of Hampden County; the queue data does not give exact sites.

Power plants in Massachusetts Β· Transmission lines in Massachusetts

Other requests in Hampden County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem