United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project R60, Sac County

Onshore wind project R60, Sac County is a 54.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Sac County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2009 (completed)
  2. Withdrawn / abandonedJan 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
R60
Grid region
MISO (Midcontinent)
Connection point (POI)
Clipper (Intrepid) - expansion
Location
Sac County, Iowa
Technology
Wind: 54.0 MW
Total requested
54.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
8 April 2009
Proposed online date
June 2010
Withdrawn
January 2017

Location

Marker shows the centre of Sac County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Sac County