Onshore wind project J535, Sac County

Onshore wind project J535, Sac County is a 210 MW onshore wind request built and operating in the MISO interconnection queue, in Sac County, Iowa.

Queue statusOperating
  1. PlanningQueued Nov 2015 (completed)
  2. ConsentedDec 2018 (completed)
  3. Construction (completed)
  4. OperatingApr 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J535
Grid region
MISO (Midcontinent)
Connection point (POI)
J411 – Lehigh 345kV Line
Location
Sac County, Iowa
Technology
Wind: 210 MW
Total requested
210 MW
Study phase
GIA
Queue status
Operational
Entered queue
16 November 2015
Agreement signed
20 December 2018
Proposed online date
April 2020
Came online
April 2020

Location

Marker shows the centre of Sac County; the queue data does not give exact sites.