OCTARY USA · INTERCONNECTION QUEUES

Battery storage interconnection queue in the USA — page 31

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,226417.8 GW
Active in queue417.8 GW2,226 requests
Agreement signed76.1 GW459 requests
Withdrawn3,516554.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,226 requests · page 31 of 45
ProjectCapacityStatusLocationRegionQueuedOnline
watermelon 8 energy storage
Battery storage · Tempus power management LLC
102 MWIn study Dallas, TXERCOT Feb 2025target 2029
Prairie Horizon Energy Storage 2
Battery storage · Tempus Power management LLC
102 MWIn study Robertson, TXERCOT Feb 2025target 2027
Edgewood BESS 1
Battery storage · Tempus Power management LLC
102 MWIn study Van Zandt, TXERCOT Nov 2024target 2028
watermelon 7 energy storage
Battery storage · Tempus power management LLC
102 MWIn study Dallas, TXERCOT Feb 2025target 2029
Blackland Prairie 3 Energy Storage
Battery storage · Tempus power management LLC
102 MWIn study Travis, TXERCOT Mar 2025target 2027
Denali Energy Storage
Battery storage
102 MWAgreement signed San Joaquin, CACAISO Apr 2020target 2028
Pajaro Valley Storage
Battery storage
102 MWIn study San Diego, CACAISO Apr 2021target 2030
Battery storage project GEN-2025-SR7, Muskogee County
Battery storage
102 MWIn study Muskogee, OKSPP May 2025target 2026
Half Moon 2 BESS
Battery storage
102 MWPaused / redesign Hidalgo, TXERCOT Mar 2022
Droga
Battery storage
102 MWIn study Merced, CACAISO Apr 2023target 2028
Tokay Storage
Battery storage
102 MWAgreement signed Santa Clara, CACAISO Apr 2021target 2030
Stoneridge BESS
Battery storage · Stoneridge Solar, LLC
102 MWAgreement signed Milam, TXERCOT Mar 2023target 2026
Pamela Heights I
Battery storage · Pamela heights I Energy Center LLC
102 MWAgreement signed Harris, TXERCOT Sep 2024target 2026
Battery storage project GEN-2023-SR27, Mayes County
Battery storage
102 MWIn study Mayes, OKSPP Jul 20232024
Rose Quartz BESS
Battery storage · Rose Quartz BESS, LLC
101 MWIn study Dimmit, TXERCOT Sep 2022target 2026
Raven Storage
Battery storage · Raven Storage, LLC
101 MWAgreement signed Wharton, TXERCOT Jan 2022target 2026
Margay Energy Storage
Battery storage · PowerPulse LLC
101 MWIn study Brazoria, TXERCOT Feb 2025target 2029
Megamouth Energy Storage
Battery storage · GCI Megamouth, LLC
101 MWAgreement signed Harris, TXERCOT Mar 2024target 2028
Pinnacle Point Energy Storage
Battery storage · GCI Pinnacle Point, LLC
101 MWIn study Harris, TXERCOT Nov 2023target 2027
Blue Creek Energy Storage
Battery storage · Blue Creek Energy Storage, LLC
101 MWIn study Wharton, TXERCOT Oct 2023target 2028
Kinney County Energy
Battery storage · Kinney County Energy, LLC
101 MWIn study Kinney, TXERCOT Mar 2023target 2027
Lyford Energy
Battery storage · Lyford Energy, LLC
101 MWIn study Willacy, TXERCOT Mar 2023target 2027
Southside Energy
Battery storage · Southside Energy, LLC
101 MWIn study Brazoria, TXERCOT Feb 2023target 2028
Citrus Flatts BESS
Battery storage · Citrus Flatts Energy Center, LLC
101 MWAgreement signed Cameron, TXERCOT Mar 2022target 2026
Hadrian Energy Storage
Battery storage · Hadrian Energy Storage, LLC
101 MWIn study Wharton, TXERCOT May 2023target 2028
Hynes Bay Energy Storage
Battery storage · Hynes Bay Energy Storage, LLC
101 MWIn study Wharton, TXERCOT Oct 2023target 2027
Saltillo Storage
Battery storage
101 MWPaused / redesign Bastrop, TXERCOT May 2022target 2025
Double Springs Energy Storage
Battery storage
101 MWAgreement signed Calaveras, CACAISO Apr 2021target 2029
Las Moras Battery
Battery storage · Las Moras Storage, LLC
101 MWIn study Kinney, TXERCOT Jun 2021target 2029
Solar Star Frontier BESS
Battery storage · Solar Star Frontier BESS, LLC
101 MWIn study Cameron, TXERCOT Jun 2023target 2029
Vaca Storage
Battery storage · Long Mount Storage, LLC
101 MWIn study Calhoun, TXERCOT Mar 2021target 2029
Carambola BESS
Battery storage · SMT McAllen II LLC
101 MWAgreement signed Hidalgo, TXERCOT Oct 2022target 2026
Sunbeam Storage
Battery storage
101 MWAgreement signed San Mateo, CACAISO Apr 2021target 2034
Paradiso BESS
Battery storage · VESI 13
101 MWAgreement signed Atascosa, TXERCOT Mar 2021target 2028
Eiger Energy Storage
Battery storage
101 MWIn study Kern, CACAISO Apr 2021target 2032
Pinewood BESS
Battery storage
101 MWPaused / redesign Brazoria, TXERCOT Sep 2022
Hide Town Energy Storage
Battery storage · Hide Town Energy Storage LLC
101 MWIn study Scurry, TXERCOT Jan 2023target 2028
Inertia BESS 2
Battery storage
101 MWPaused / redesign Haskell, TXERCOT Oct 2020
Venus Mill Storage
Battery storage
101 MWPaused / redesign Ellis, TXERCOT Mar 2022target 2026
Padrino BESS
Battery storage
101 MWPaused / redesign Hill, TXERCOT Sep 2022
Picadillo BESS
Battery storage · Black Mountain Energy Storage II
101 MWAgreement signed Martin, TXERCOT Mar 2022target 2028
Hana Springs BESS
Battery storage · Black Mountain Energy Storage II LLC
101 MWIn study Lampasas, TXERCOT Nov 2022target 2028
Calf Creek Storage
Battery storage · Coyote Ridge Storage, LLC
101 MWIn study Howard, TXERCOT Nov 2025target 2028
Rutile BESS
Battery storage · Rutile BESS, LLC
101 MWAgreement signed Runnels, TXERCOT Jan 2023target 2028
Dolce BESS
Battery storage · Dolce BESS, LLC
101 MWIn study Mitchell, TXERCOT Sep 2022target 2028
Ringtail Ridge Storage
Battery storage · KCE TX 26, LLC
101 MWIn study Kendall, TXERCOT Jan 2021target 2028
Mobee Springs BESS
Battery storage · Mobee Springs, LLC
101 MWIn study Refugio, TXERCOT Jun 2025target 2028
BRP Diran BESS
Battery storage · BRP Diran BESS LLC
101 MWAgreement signed Wharton, TXERCOT Dec 2020target 2028
Sugarloaf BESS
Battery storage · Sugarloaf Clean Energy LLC
101 MWIn study Dimmit, TXERCOT Mar 2024target 2028
Sagewood BESS
Battery storage · Sagewood BESS, LLC
101 MWIn study Glasscock, TXERCOT Sep 2022target 2028
Page 31 of 45

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)