United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

BATTERY STORAGE Β· ERCOT

Saltillo Storage

Saltillo Storage is a 101 MW battery storage request suspended in the ERCOT interconnection queue, in Bastrop County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued May 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0073
Grid region
ERCOT (Texas)
Location
Bastrop County, Texas
Technology
Battery: 101 MW
Total requested
101 MW
Queue status
Suspended
Entered queue
9 May 2022
Proposed online date
June 2025

Location

Marker shows the centre of Bastrop County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Bastrop County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem