Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown905105.4 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

905 requests · page 3 of 19
ProjectCapacityStatusLocationRegionQueuedOnline
South Branch Solar
Solar
205 MWPaused / redesign Hancock, OHPJM Aug 2017target 2025
Axton Solar
Solar
201 MWPaused / redesign Henry, VAPJM Mar 2019target 2025
Solar project AH2-397, Somerset County
Solar
200 MWIn study Somerset, PAPJM Mar 2022target 2026
CPV Wilson Solar
Solar · CPV Wilson Solar, LLC
200 MWIn study Garrett, MDPJM Mar 2025target 2024
Solar project AH1-580, Harrison County
Solar · Energy Pastures Solar Project, LLC
200 MWIn study Harrison, OHPJM Mar 2025target 2025
Solar project AG2-104, Madison County
Solar · Oak Run Solar Project, LLC
200 MWIn study Madison, OHPJM Mar 2025target 2025
Solar project AG2-182, Frederick County
Solar · ACE Development Company, LLC
200 MWIn study Frederick, VAPJM Feb 2025target 2022
Solar + storage project AI1-039, Clearfield County
Solar + storage
200 MWIn study Clearfield, PAPJM Apr 2022target 2025
Battery storage project AG2-329, Wyandot County
Battery storage · Wombat Solar LLC
200 MWIn study Wyandot, OHPJM Mar 2025target 2024
Solar + storage project AH2-025, Fountain County
Solar + storage
200 MWIn study Fountain, INPJM Oct 2021target 2027
Solar + storage project AI1-134, Grant County
Solar + storage
200 MWIn study Grant, INPJM Sep 2022target 2029
Battery storage project AH2-102, Franklin County
Battery storage
200 MWIn study Franklin, VAPJM Jan 2022target 2026
Battery storage project AH2-378A, Gloucester County
Battery storage
200 MWIn study Gloucester, NJPJM Mar 2022target 2025
Solar + storage project AH2-043, Kanawha County
Solar + storage
200 MWIn study Kanawha, WVPJM Nov 2021target 2025
Solar + storage project AH2-363, Kankakee County
Solar + storage
200 MWIn study Kankakee, ILPJM Mar 2022target 2027
Solar project AH1-151, Lee County
Solar · Steward Creek Solar, LLC
200 MWIn study Lee, ILPJM Feb 2025target 2025
Battery storage project AH2-051, New Castle County
Battery storage
200 MWIn study New Castle, DEPJM Dec 2021target 2025
Solar project AH1-150, Lee County
Solar · Steward Creek Solar, LLC
200 MWIn study Lee, ILPJM Feb 2025target 2025
Battery storage project AH1-263, Spotsylvania County
Battery storage · Scarlet Energy Storage LLC
200 MWIn study Spotsylvania, VAPJM Feb 2025target 2025
Battery storage project AH2-265, Charles County
Battery storage
200 MWIn study Charles, MDPJM Mar 2022target 2026
Solar project AI1-103, Champaign County
Solar
200 MWIn study Champaign, OHPJM Aug 2022target 2029
Battery storage project AI1-013, Charles City County
Battery storage
200 MWIn study Charles City, VAPJM Apr 2022target 2026
Battery storage project AH2-103, Fayette County
Battery storage
200 MWIn study Fayette, PAPJM Feb 2022target 2026
Steward Creek Solar
Solar · Steward Creek Solar, LLC
200 MWIn study Lee, ILPJM Mar 2020target 2023
Onshore wind project AI1-168, Coshocton County
Onshore wind
200 MWIn study Coshocton, OHPJM Sep 2022target 2027
South Dixon Solar
Solar · Deriva Energy Solar, LLC
200 MWIn study Lee, ILPJM Sep 2019target 2022
Onshore wind project AI1-191, Stephenson County
Onshore wind
200 MWIn study Stephenson, ILPJM Sep 2022target 2027
Cornerstone Solar
Solar · Cornerstone Solar, LLC
200 MWIn study Washington, PAPJM Feb 2025target 2025
Solar project AG2-364, Tazewell County
Solar · Mackinaw Solar LLC
200 MWIn study Tazewell, ILPJM Mar 2025target 2024
Solar project AH1-617
Solar · STMO bn, LLC
200 MWIn study KYPJM Feb 2025target 2024
Teays River Wind Farm
Onshore wind · Teays River Wind Farm LLC f/k/a Blackford County Wind Farm LLC
200 MWIn study Blackford, INPJM Mar 2020target 2023
Solar project AG2-082, Harrison County
Solar · Energy Pastures Solar Project, LLC
200 MWIn study Harrison, OHPJM Mar 2025target 2024
Cass County Solar
Solar + storage · Steelhead Solar, LLC
200 MWIn study Cass, MIPJM Mar 2020target 2023
Riverbank Energy
Battery storage · Lincoln Reserve Energy, LLC
200 MWIn study Cook, ILPJM Mar 2020target 2024
Battery storage project AH2-347, St. Joseph County
Battery storage
200 MWIn study St. Joseph, INPJM Mar 2022target 2025
Battery storage project AI1-023, Mclean County
Battery storage
200 MWIn study Mclean, ILPJM Apr 2022target 2026
Solar project AG2-077, Charlotte County
Solar · Virginia Electric and Power Company
200 MWIn study Charlotte, VAPJM Jan 2025target 2024
Battery storage project AG2-544, Mchenry County
Battery storage · Monarch Grid, LLC
200 MWIn study Mchenry, ILPJM Mar 2025target 2024
Solar project AH1-044, Lee County
Solar · Steward Creek Solar, LLC
200 MWIn study Lee, ILPJM Feb 2025target 2024
Lower Crossing Wind
Onshore wind
200 MWPaused / redesign Kankakee, ILPJM Jan 2018target 2026
Onshore wind project AH2-386, Pendleton County
Onshore wind
192 MWIn study Pendleton, WVPJM Mar 2022target 2027
Gipper Wind Farm
Onshore wind · Gipper Wind Farm, LLC
191 MWIn study Whiteside, ILPJM Sep 2019target 2022
Martin County Solar Project
Solar
190 MWPaused / redesign Martin, KYPJM Sep 2019target 2028
Solar project AH1-272, Van Buren County
Solar · Bankson Solar Project, LLC
185 MWIn study Van Buren, MIPJM Feb 2025target 2025
Solar project AH2-168, Madison County
Solar
185 MWIn study Madison, OHPJM Mar 2022target 2025
Solar + storage project AI1-212, Jefferson County
Solar + storage
182 MWIn study Jefferson, PAPJM Sep 2022target 2024
Solar + storage project AH2-153, Vermillion County
Solar + storage
180 MWIn study Vermillion, INPJM Feb 2022target 2024
Solar + storage project AH2-373, Berrien County
Solar + storage
180 MWIn study Berrien, MIPJM Mar 2022target 2028
Battery storage project AH2-423, Calvert County
Battery storage
180 MWIn study Calvert, MDPJM Mar 2022target 2025
Solar project AH1-338, Lee County
Solar · Prairie Brome Solar LLC
180 MWIn study Lee, ILPJM Feb 2025target 2025
Page 3 of 19

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)