Withdrawn queue requests in the USA — page 250

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 250 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project C1-33, San Juan County
Solar
100 MWWithdrawn / abandoned San Juan, UTWest May 2021target 2024
Onshore wind project G747, Rock County
Onshore wind
100 MWWithdrawn / abandoned Rock, WIMISO Feb 2007
Solar project J326, Chisago County
Solar
100 MWWithdrawn / abandoned Chisago, MNMISO Mar 2014target 2016
Battery storage project AG2-084, Howard County
Battery storage · Locomotive Solar, LLC
100 MWWithdrawn / abandoned Howard, INPJM Jan 2021target 2023
Onshore wind project GEN-2007-010N03, Lincoln County
Onshore wind
100 MWWithdrawn / abandoned Lincoln, NESPP Mar 2007
Enel NYPA Astoria
Battery storage · Enel Energy Storage Holdings, LLC
100 MWWithdrawn / abandoned Queens, NYNYISO Oct 2019
Solar project J1825, Decatur County
Solar
100 MWWithdrawn / abandoned Decatur, INMISO Jun 2020target 2024
Sullivan-Woodbourne Solar Project
Solar · New York Power Authority
100 MWWithdrawn / abandoned Sullivan, NYNYISO Sep 2024
Solar + storage project J2625, Marion County
Solar + storage
100 MWWithdrawn / abandoned Marion, MOMISO Sep 2022target 2026
Gas project G28, Clark County
Gas
100 MWWithdrawn / abandoned Clark, WAWest Feb 2001target 2001
North Foothills Solar
Solar · North Foothills Energy Center, LLC
100 MWWithdrawn / abandoned Franklin, NYNYISO Oct 2024
Solar + storage project C2-77, Box Elder County
Solar + storage
100 MWWithdrawn / abandoned Box Elder, UTWest May 2022target 2027
Western Door Wind
Onshore wind · Western Door Wind, LLC
100 MWWithdrawn / abandoned Yates, NYNYISO Jan 2007
Solar project IC-439, Decatur County
Solar
100 MWWithdrawn / abandoned Decatur, GASoutheast Feb 2016
Solar + storage project J2072, Grant County
Solar + storage
100 MWWithdrawn / abandoned Grant, ARMISO Aug 2021target 2024
Solar project IC-1161, Greene County
Solar
100 MWWithdrawn / abandoned Greene, GASoutheast Aug 2023target 2026
Gas project 22, Twin Falls County
Gas
100 MWWithdrawn / abandoned Twin Falls, IDWest Apr 2001target 2001
Battery storage project J2557, Wood County
Battery storage
100 MWWithdrawn / abandoned Wood, WIMISO Sep 2022target 2029
Sugar Solar LLC
Solar · Sugar Solar, LLC
100 MWWithdrawn / abandoned Campbell, VAPJM Feb 2025target 2026
Onshore wind project J927, Faribault County
Onshore wind
100 MWWithdrawn / abandoned Faribault, MNMISO Jun 2017target 2021
Solar project J2182, Tallahatchie County
Solar
100 MWWithdrawn / abandoned Tallahatchie, MSMISO Aug 2021target 2025
Battery storage project J1435, Dubuque County
Battery storage
100 MWWithdrawn / abandoned Dubuque, IAMISO Apr 2019target 2022
Solar project J1449, Monroe County
Solar
100 MWWithdrawn / abandoned Monroe, MIMISO Apr 2019target 2022
Solar project J2491, Midland County
Solar
100 MWWithdrawn / abandoned Midland, MIMISO Sep 2022target 2025
Battery storage project Q52, Maricopa County
Battery storage
100 MWWithdrawn / abandoned Maricopa, AZWest Dec 2018target 2023
Battery storage project AE1-002, Benton County
Battery storage
100 MWWithdrawn / abandoned Benton, INPJM Apr 2018target 2020
Solar + storage project Company KA, Mineral County
Solar + storage
100 MWWithdrawn / abandoned Mineral, NVWest Sep 2019target 2022
McHenry County Solar Project
Solar · McHenry County Solar Project, LLC
100 MWWithdrawn / abandoned Mchenry, ILPJM Mar 2019target 2021
Evergreen Storage
Other · Evergreen Energy LLC
100 MWWithdrawn / abandoned Matagorda, TXERCOT Jun 2022target 2025
Onshore wind project G554, Palo Alto County
Onshore wind
100 MWWithdrawn / abandoned Palo Alto, IAMISO Oct 2005target 2007
Battery storage project GEN-2024-256, Cass County
Battery storage
100 MWWithdrawn / abandoned Cass, MOSPP Mar 2025target 2030
Solar project GEN-2018-097, Parmer County
Solar
100 MWWithdrawn / abandoned Parmer, TXSPP Nov 2018target 2027
Battery storage project 14, Sacramento County
Battery storage
100 MWWithdrawn / abandoned Sacramento, CAWest Nov 2021target 2024
Elmer Battery
Other · Energy Storage Resources, LLC
100 MWWithdrawn / abandoned Tarrant, TXERCOT May 2019target 2021
Other project IC-245, Clarke County
Other
100 MWWithdrawn / abandoned Clarke, MSSoutheast Dec 2010
Onshore wind project J064, Beltrami County
Onshore wind
100 MWWithdrawn / abandoned Beltrami, MNMISO Aug 2009target 2011
Solar project 20171018008, Orangeburg County
Solar
100 MWWithdrawn / abandoned Orangeburg, SCSoutheast target 2023
Solar project J3806, Sunflower County
Solar
100 MWWithdrawn / abandoned Sunflower, MSMISO Apr 2024target 2028
Hylton Mountain
Onshore wind · Gamesa Energia SW
100 MWWithdrawn / abandoned ERCOT Mar 2005target 2050
Solar + storage project 2023-G3, San Joaquin County
Solar + storage
100 MWWithdrawn / abandoned San Joaquin, CAWest Mar 2023target 2026
Solar project GI-2016-16, Pueblo County
Solar
100 MWWithdrawn / abandoned Pueblo, COWest Aug 2016target 2018
Solar project AD2-207, Isle Of Wight County
Solar
100 MWWithdrawn / abandoned Isle Of Wight, VAPJM Mar 2018target 2020
Onshore wind project Q16, Coconino County
Onshore wind
100 MWWithdrawn / abandoned Coconino, AZWest Sep 2005target 2007
Solar project J1228, Faribault County
Solar
100 MWWithdrawn / abandoned Faribault, MNMISO Apr 2019target 2023
Solar project J1473, Chisago County
Solar
100 MWWithdrawn / abandoned Chisago, MNMISO Apr 2019target 2022
Battery storage project GEN-2023-214, Bryan County
Battery storage
100 MWWithdrawn / abandoned Bryan, OKSPP Oct 2023target 2028
Solar project Company 143, Clark County
Solar
100 MWWithdrawn / abandoned Clark, NVWest Jan 2015target 2017
Onshore wind project J608, Montcalm County
Onshore wind
100 MWWithdrawn / abandoned Montcalm, MIMISO May 2016target 2018
Onshore wind project R65, Ogle County
Onshore wind
100 MWWithdrawn / abandoned Ogle, ILPJM Jan 2007target 2010
Loraine Windpark Phase III
Onshore wind · Third Planet Wind Power
100 MWWithdrawn / abandoned Mitchell, TXERCOT Aug 2017target 2024
Page 250 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)