ONSHORE WIND · ERCOT

Loraine Windpark Phase III

Loraine Windpark Phase III is a 100 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Mitchell County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2017 (completed)
  2. Withdrawn / abandonedJul 2023 (project stopped here)
  3. ConsentedApr 2018 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
18INR0068
Grid region
ERCOT (Texas)
Developer
Third Planet Wind Power
Connection point (POI)
181153 Lonewolf 345kV
Location
Mitchell County, Texas
Technology
Wind: 100 MW
Total requested
100 MW
Study phase
IA and FIS Pending
Queue status
Withdrawn
Entered queue
13 August 2017
Agreement signed
10 April 2018
Proposed online date
May 2024
Withdrawn
July 2023

Location

Marker shows the centre of Mitchell County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Mitchell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem