BATTERY STORAGE Β· PJMBattery storage project AE1-002, Benton County
Battery storage project AE1-002, Benton County is a 100 MW battery storage request withdrawn in the PJM interconnection queue, in Benton County, Indiana, connecting to ComEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2018 (completed)
- Withdrawn / abandonedJul 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AE1-002
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Wilton Center-Loretto
- Location
- Benton County, Indiana
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 4 April 2018
- Proposed online date
- December 2020
- Withdrawn
- July 2019
Location
Marker shows the centre of Benton County; the queue data does not give exact sites.
Other requests in Benton County
- Onshore wind project J1470, Benton CountyOnshore wind Β· 30.0 MW Β· agreement signed
- Onshore wind project J2440, Benton CountyOnshore wind Β· 100 MW Β· in study
- Onshore wind project J2048, Benton CountyOnshore wind Β· 100 MW Β· in study
- Fowler Ridge WFOnshore wind Β· 500 MW Β· built
- Onshore wind project J515, Benton CountyOnshore wind Β· 400 MW Β· built
- Fowler Ridge 4 WFOnshore wind Β· 250 MW Β· built
- Meadow Lake WF II, Meadow Lake WF IIIOnshore wind Β· 200 MW Β· built
- Onshore wind project J431, Benton CountyOnshore wind Β· 100 MW Β· built
- Onshore wind project N001, Benton CountyOnshore wind Β· 100 MW Β· built
- Onshore wind project G439, Benton CountyOnshore wind Β· 100 MW Β· built
- Onshore wind project G606, Benton CountyOnshore wind Β· 30.0 MW Β· built
- Onshore wind project AD2-015, Benton CountyOnshore wind Β· 500 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem