United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2021 requests) โ page 25
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project IC-969, Bullock County Solar |
79.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-930, Macon County Solar + storage |
79.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-928, Dale County Solar + storage |
79.0 MW | Withdrawn / abandoned |
| Solar + storage project AG2-465, Seneca County Solar + storage |
79.0 MW | Withdrawn / abandoned |
| Solar + storage project J2137, Ohio County Solar + storage |
78.2 MW | Withdrawn / abandoned |
| Battery storage project J1869, Winn Parish County Battery storage |
78.0 MW | Withdrawn / abandoned |
| Solar project AG2-190, Carroll County Solar |
77.4 MW | Withdrawn / abandoned |
| Solar + storage project AG2-603, Carroll County Solar + storage ยท Issa Solar LLC |
77.0 MW | Withdrawn / abandoned |
| Breckenridge Battery storage |
76.5 MW | Withdrawn / abandoned |
| Solar project AH1-620, Queen Anne's County Solar |
76.0 MW | Withdrawn / abandoned |
| Battery storage project J2315, Liberty County Battery storage |
75.3 MW | Withdrawn / abandoned |
| Battery storage project J1875, Union County Battery storage |
75.0 MW | Withdrawn / abandoned |
| Battery storage project J1874, Union County Battery storage |
75.0 MW | Withdrawn / abandoned |
| Solar project AG2-153, Bourbon County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project AH1-103, Caroline County Solar |
75.0 MW | Withdrawn / abandoned |
| Salt Rush Wind Onshore wind ยท Invenergy Wind Development North America LLC |
75.0 MW | Withdrawn / abandoned |
| Battery storage project J2005, Deuel County Battery storage |
75.0 MW | Withdrawn / abandoned |
| ACE Development Company, LLC Solar ยท ACE Development Company, LLC |
75.0 MW | Withdrawn / abandoned |
| Twinleaf Solar Solar ยท Invenergy Solar Project Development LLC |
75.0 MW | Withdrawn / abandoned |
| Wintergreen Solar Solar ยท Invenergy Solar Project Development LLC |
75.0 MW | Withdrawn / abandoned |
| Battery storage project AG2-318, Spotsylvania County Battery storage |
75.0 MW | Withdrawn / abandoned |
| Solar project Q404, Maricopa County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-953, Perry County Solar + storage |
75.0 MW | Withdrawn / abandoned |
| Battery storage project AH1-303, Vermillion County Battery storage |
75.0 MW | Withdrawn / abandoned |
| Battery storage project GEN-2021-051, Henry County Battery storage |
75.0 MW | Withdrawn / abandoned |
| Battery storage project J1937, Portage County Battery storage |
75.0 MW | Withdrawn / abandoned |
| Battery storage project J1936, Portage County Battery storage |
75.0 MW | Withdrawn / abandoned |
| Glenwood BESS Battery storage ยท Juno Power Management LLC |
75.0 MW | Withdrawn / abandoned |
| Solar project J1962, Polk County Solar |
75.0 MW | Withdrawn / abandoned |
| Surplus; J850 Other |
75.0 MW | Withdrawn / abandoned |
| Solar project 160 Solar |
75.0 MW | Withdrawn / abandoned |
| Shovelnose Energy Storage Battery storage |
75.0 MW | Withdrawn / abandoned |
| Pine Barrens Storage Battery storage ยท Pine Barrens Storage LLC |
75.0 MW | Withdrawn / abandoned |
| Solar + storage project AH1-342, Allegany County Solar + storage |
75.0 MW | Withdrawn / abandoned |
| Solar project AH1-362, Mecklenburg County Solar |
75.0 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2021-022, Kiowa County Onshore wind |
75.0 MW | Withdrawn / abandoned |
| Arcade Solar Solar ยท Arcade Solar, LLC |
75.0 MW | Withdrawn / abandoned |
| Solar project 80, Hillsborough County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 291, Wakulla County Solar ยท Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project GEN-2021-015, Ellis County Solar |
74.9 MW | Withdrawn / abandoned |
| Battery storage project GEN-2021-013, Lincoln County Battery storage |
74.9 MW | Withdrawn / abandoned |
| Solar project 78, Hillsborough County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 79, Hillsborough County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 294, Gilchrist County Solar ยท Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar + storage project Q382, Pinal County Solar + storage |
74.9 MW | Withdrawn / abandoned |
| Solar project 81, Hillsborough County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project GEN-2021-011, Cloud County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 299, Manatee County Solar ยท Masked |
74.5 MW | Withdrawn / abandoned |
| Solar project 298, Manatee County Solar ยท Masked |
74.5 MW | Withdrawn / abandoned |
| Solar project 423, St. Lucie County Solar ยท FPL |
74.5 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)220 ยท 82.8 GW
- West (non-ISO utilities)339 ยท 78.3 GW
- PJM (Mid-Atlantic, Midwest)819 ยท 65.0 GW
- MISO (Midcontinent)267 ยท 38.5 GW
- NYISO (New York)149 ยท 23.5 GW
- Southeast (non-ISO utilities)123 ยท 16.3 GW
- ERCOT (Texas)77 ยท 13.4 GW
- SPP (Southwest Power Pool)70 ยท 13.1 GW
- ISO-NE (New England)85 ยท 8,317 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)