United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

BATTERY STORAGE Β· MISO

Battery storage project J2005, Deuel County

Battery storage project J2005, Deuel County is a 75.0 MW battery storage request withdrawn in the MISO interconnection queue, in Deuel County, South Dakota, connecting to OTTER TAIL POWER COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2005
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Astoria 345kV
Location
Deuel County, South Dakota
Technology
Battery: 75.0 MW
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
26 August 2021
Proposed online date
October 2026
Withdrawn
October 2023

Location

Marker shows the centre of Deuel County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Deuel County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem