United States › Grid › Interconnection queues › North Carolina
SOLAR · PJMACE Development Company, LLC
ACE Development Company, LLC is a 75.0 MW solar request withdrawn in the PJM interconnection queue, in Northampton County, North Carolina, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2021 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-434
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Developer
- ACE Development Company, LLC
- Connection point (POI)
- Carolina- Earleys 115kV
- Location
- Northampton County, North Carolina
- Technology
- Solar: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Withdrawn
- Entered queue
- 10 September 2021
- Proposed online date
- September 2026
- Withdrawn
- July 2025
Location
Marker shows the centre of Northampton County; the queue data does not give exact sites.
Power plants in North Carolina · Transmission lines in North Carolina
Other requests in Northampton County
- Cherry SolarSolar · 180 MW · agreement signed
- Oak SolarSolar · 120 MW · built
- Gutenberg SolarSolar · 74.9 MW · built
- Spuds Lane Solar ParkSolar · 74.9 MW · built
- Gutenberg SolarSolar · 5.0 MW · built
- Solar project AC2-093, Northampton CountySolar · 675 MW · withdrawn
- Solar project AA1-064, Northampton CountySolar · 80.0 MW · withdrawn
- Solar project AA2-181, Northampton CountySolar · 80.0 MW · withdrawn
- Solar project AC2-159, Northampton CountySolar · 80.0 MW · withdrawn
- Solar project AB2-128, Northampton CountySolar · 80.0 MW · withdrawn
- Solar project AA1-137, Northampton CountySolar · 80.0 MW · withdrawn
- Solar project AG1-313, Northampton CountySolar · 46.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem