United States › Grid › Interconnection queues › North Carolina
SOLAR · PJMSpuds Lane Solar Park
Spuds Lane Solar Park is a 74.9 MW solar request built and operating in the PJM interconnection queue, in Northampton County, North Carolina, connecting to Dominion.
Request details
- Queue ID
- AA1-063A
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Carolina–Seaboard 115kV
- Location
- Northampton County, North Carolina
- Technology
- Solar: 74.9 MW
- Total requested
- 74.9 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 29 September 2014
- Agreement signed
- 14 December 2018
- Proposed online date
- August 2018
- Came online
- November 2018
Location
Marker shows the centre of Northampton County; the queue data does not give exact sites.
Power plants in North Carolina · Transmission lines in North Carolina
Other requests in Northampton County
- Cherry SolarSolar · 180 MW · agreement signed
- Oak SolarSolar · 120 MW · built
- Gutenberg SolarSolar · 74.9 MW · built
- Gutenberg SolarSolar · 5.0 MW · built
- Solar project AC2-093, Northampton CountySolar · 675 MW · withdrawn
- Solar project AA1-064, Northampton CountySolar · 80.0 MW · withdrawn
- Solar project AA2-181, Northampton CountySolar · 80.0 MW · withdrawn
- Solar project AC2-159, Northampton CountySolar · 80.0 MW · withdrawn
- Solar project AB2-128, Northampton CountySolar · 80.0 MW · withdrawn
- Solar project AA1-137, Northampton CountySolar · 80.0 MW · withdrawn
- ACE Development Company, LLCSolar · 75.0 MW · withdrawn
- Solar project AG1-313, Northampton CountySolar · 46.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem