BATTERY STORAGE · NYISO

Pine Barrens Storage

Pine Barrens Storage is a 75.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Suffolk County, New York, connecting to LIPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1301
Grid region
NYISO (New York)
Utility / transmission owner
LIPA
Developer
Pine Barrens Storage LLC
Connection point (POI)
Brookhaven 138 kV Substation
Location
Suffolk County, New York
Technology
Battery: 75.0 MW
Total requested
75.0 MW
Queue status
Withdrawn
Entered queue
9 November 2021

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Suffolk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem