Solar project 423, St. Lucie County

Solar project 423, St. Lucie County is a 74.5 MW solar request withdrawn in the Southeast interconnection queue, in St. Lucie County, Florida, connecting to Florida Power & Light.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
423
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
FPL
Connection point (POI)
Southern St Lucie County
Location
St. Lucie County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
11 May 2021
Proposed online date
December 2028

Location

Marker shows the centre of St. Lucie County; the queue data does not give exact sites.

Power plants in Florida Β· Transmission lines in Florida

Other requests in St. Lucie County