OTHER Β· MISOSurplus; J850
Surplus; J850 is a 75.0 MW other request withdrawn in the MISO interconnection queue, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2021 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- S1006
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- REC Bradford - W. Darien 138kV Line
- Technology
- Other: 75.0 MW Β· Battery
- Total requested
- 75.0 MW
- Queue status
- Withdrawn
- Entered queue
- 2 April 2021
- Proposed online date
- October 2023
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem