United States βΊ Grid βΊ Interconnection queues βΊ Texas
BATTERY STORAGE Β· MISOBattery storage project J2315, Liberty County
Battery storage project J2315, Liberty County is a 75.3 MW battery storage request withdrawn in the MISO interconnection queue, in Liberty County, Texas, connecting to ENTERGY TEXAS, INC..
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2021 (completed)
- Withdrawn / abandonedOct 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2315
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY TEXAS, INC.
- Connection point (POI)
- Petry Woods
- Location
- Liberty County, Texas
- Technology
- Battery: 75.3 MW
- Total requested
- 75.3 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 10 September 2021
- Proposed online date
- December 2023
- Withdrawn
- October 2023
Location
Marker shows the centre of Liberty County; the queue data does not give exact sites.
Other requests in Liberty County
- Solar project J1760, Liberty CountySolar Β· 205 MW Β· agreement signed
- Solar project J483, Liberty CountySolar Β· 100 MW Β· agreement signed
- Solar project J3986, Liberty CountySolar Β· 270 MW Β· in study
- Solar project J2075, Liberty CountySolar Β· 200 MW Β· in study
- Solar + storage project J2689, Liberty CountySolar + storage Β· 180 MW Β· in study
- Solar project J2314, Liberty CountySolar Β· 150 MW Β· in study
- Solar project J2165, Liberty CountySolar Β· 145 MW Β· in study
- Gas project J3605, Liberty CountyGas Β· 465 MW Β· withdrawn
- Solar project J2767, Liberty CountySolar Β· 200 MW Β· withdrawn
- Onshore wind project J3972, Liberty CountyOnshore wind Β· 200 MW Β· withdrawn
- Noor SolarSolar Β· 188 MW Β· withdrawn
- Solar project J1277, Liberty CountySolar Β· 130 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem