BATTERY STORAGE Β· MISO

Battery storage project J1869, Winn Parish County

Battery storage project J1869, Winn Parish County is a 78.0 MW battery storage request withdrawn in the MISO interconnection queue, in Winn Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1869
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
Winnfield to Standard 115kV
Location
Winn Parish County, Louisiana
Technology
Battery: 78.0 MW
Total requested
78.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 August 2021
Proposed online date
September 2024
Withdrawn
October 2023

Location

Marker shows the centre of Winn Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in Winn Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem