United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in the USA (2015 requests) β€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7315.8 GW
Active in queue15.8 GW73 requests
Agreement signed8,536 MW38 requests
Withdrawn80095.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

73 requests Β· page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J514, Marshall County
Gas
65.0 MWAgreement signed Marshall, IAMISO Nov 2015target 2017
Solar project BHCT G19, Pueblo County
Solar
60.0 MWIn study Pueblo, COWest Apr 2015target 2019
Solar + storage project 642, Iron County
Solar + storage Β· Parowan Solar, LLC
58.0 MWIn study Iron, UTWest Feb 2015target 2024
Chatee Solar
Solar Β· Hecate Energy
57.0 MWPaused / redesign Pecos, TXERCOT Apr 2015target 2020
Battery storage project Q229, Maricopa County
Battery storage
50.0 MWIn study Maricopa, AZWest Sep 2015target 2021
Solar project J504, Linn County
Solar
50.0 MWAgreement signed Linn, IAMISO Nov 20152024
Solar project J523, Mower County
Solar
50.0 MWAgreement signed Mower, MNMISO Nov 20152024
Gas project J485, Olmsted County
Gas
46.9 MWAgreement signed Olmsted, MNMISO Oct 20152018
Solar project 39, Orangeburg County
Solar
42.0 MWUnder construction Orangeburg, SCSoutheast Jun 2015target 2016
Little Bear 3
Solar + storage
40.4 MWAgreement signed Fresno, CACAISO Apr 20152020
Mountaineer #1
Coal
36.0 MWAgreement signed WVPJM Oct 20152018
Hecate Solar
Solar Β· Hecate Energy
33.0 MWPaused / redesign Brewster, TXERCOT Mar 2015target 2020
Battery storage project J466, Huron County
Battery storage
30.0 MWAgreement signed Huron, MIMISO May 2015target 2015
Geothermal project IA-PNM-2015-01, Doña Ana Cty County
Geothermal Β· ORNI 24
29.0 MWAgreement signed Doña Ana Cty, NMWest Jul 2015target 2021
Solar project G0516, Sherman County
Solar
20.0 MWIn study Sherman, ORWest Oct 2015target 2016
Other project G0505, Lincoln County
Other
20.0 MWIn study Lincoln, ORWest Jan 2015target 2017
Solar project G0513, Morrow County
Solar
20.0 MWIn study Morrow, ORWest Sep 2015target 2016
Mirage
Gas
11.0 MWPaused / redesign Harris, TXERCOT Feb 2015
Lake Alpaugh Battery Storage
Battery storage
10.0 MWAgreement signed Tulare, CACAISO Apr 2015target 2026
Altamont Midway LTD
Onshore wind
5.0 MWAgreement signed Alameda, CACAISO Apr 2015target 2027
Cedar Lane Solar
Solar
4.0 MWAgreement signed Queen Anne's, MDPJM Oct 2015target 2026
Solar project 11
Solar
2.0 MWAgreement signed FLSoutheast Aug 2015target 2016
NEA Bell. Uprate (Northeast Energy Associates, LP)
Gas
1.4 MWAgreement signed Norfolk, MAISO-NE Mar 2015target 2018
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)