SOLAR + STORAGE · CAISOLittle Bear 3
Little Bear 3 is a 40.4 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.
Queue statusConsented
- PlanningQueued Apr 2015 (completed)
- ConsentedNov 2017 (current stage)
- Construction (not yet reached)
- OperatingDec 2020 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 1127
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Mendota Substation 115kV
- Location
- Fresno County, California
- Technology
- Solar: 20.4 MW · Battery: 20.0 MW
- Total requested
- 40.4 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 30 April 2015
- Agreement signed
- 28 November 2017
- Proposed online date
- February 2029
- Came online
- December 2020
Location
Marker shows the centre of Fresno County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Fresno County
- DardenSolar + storage · 2,365 MW · agreement signed
- ScarletSolar + storage · 800 MW · agreement signed
- Cornucopia HybridSolar + storage · 605 MW · agreement signed
- Lock StorageBattery storage · 508 MW · agreement signed
- ElysianSolar + storage · 412 MW · agreement signed
- ClarksonSolar + storage · 408 MW · agreement signed
- SonrisaSolar + storage · 384 MW · agreement signed
- Luna Valley SolarSolar + storage · 373 MW · agreement signed
- Key Storage 1Battery storage · 309 MW · agreement signed
- Ciervo Mountain HybridSolar + storage · 255 MW · agreement signed
- Midway PeakingGas · 240 MW · agreement signed
- Heartland 2Solar + storage · 228 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem