🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in the USA (2019 requests) — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown20239.8 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

202 requests · page 2 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Rockefeller Solar
Solar
208 MWPaused / redesign Schleicher, TXERCOT Oct 2019target 2027
Shaula III Solar
Solar + storage · Shaula Energy Project III, LLC
205 MWIn study Dewitt, TXERCOT Dec 2019target 2025
Axton Solar
Solar
201 MWPaused / redesign Henry, VAPJM Mar 2019target 2025
Texas Solar Nova 3
Solar · Texas Solar Nova 1, LLC
200 MWIn study Kent, TXERCOT Jun 2019target 2026
Solar project J1444, Linn County
Solar
200 MWIn study Linn, IAMISO Apr 2019target 2025
Garnet Energy Center
Solar · Garnet Energy Center, LLC
200 MWIn study Cayuga, NYNYISO Jun 2019target 2028
Onshore wind project 360, Wheatland County
Onshore wind
200 MWPaused / redesign Wheatland, MTWest Feb 2019target 2021
Union City Storage I
Battery storage
200 MWIn study Fulton, GASoutheast Dec 20192022
Onshore wind project J1270, Palo Alto County
Onshore wind
200 MWIn study Palo Alto, IAMISO Apr 2019target 2024
South Dixon Solar
Solar · Deriva Energy Solar, LLC
200 MWIn study Lee, ILPJM Sep 2019target 2022
Solar + storage project 99, Franklin County
Solar + storage
200 MWIn study Franklin, WAWest Sep 2019target 2021
Hemlock Ridge Solar
Solar · Hemlock Ridge Solar LLC
200 MWIn study Orleans, NYNYISO Nov 2019target 2028
Solar project G0625, Morrow County
Solar
191 MWIn study Morrow, ORWest Jun 2019target 2020
Gipper Wind Farm
Onshore wind · Gipper Wind Farm, LLC
191 MWIn study Whiteside, ILPJM Sep 2019target 2022
Martin County Solar Project
Solar
190 MWPaused / redesign Martin, KYPJM Sep 2019target 2028
Battery storage project GEN-2019-065, Smith County
Battery storage
180 MWIn study Smith, TXSPP May 2019target 2026
Scarlet Solar
Solar · Innovative Solar 416, LLC
180 MWIn study Castro, TXERCOT Dec 2019target 2025
Onshore wind project J1365, Tama County
Onshore wind
169 MWIn study Tama, IAMISO Apr 2019target 2024
Carol Battery
Battery storage
168 MWPaused / redesign Potter, TXERCOT Jun 2019
Erie East Energy
Battery storage
160 MWPaused / redesign Erie, PAPJM Mar 2019target 2026
Solar + storage project 2019-G42, San Bernardino County
Solar + storage
160 MWIn study San Bernardino, CAWest Jun 2019target 2021
Maleza Storage
Solar + storage · Brush Storage, LLC
151 MWIn study Wharton, TXERCOT Oct 2019target 2027
Bowfin Solar
Solar + storage
150 MWPaused / redesign Huntington, INPJM Aug 2019target 2028
Bright Stalk Generating Facility
Onshore wind · Lexington Chenoa Wind Farm LLC
150 MWIn study Mclean, ILPJM Mar 2019target 2022
Solar project J1221, Wadena County
Solar
150 MWIn study Wadena, MNMISO Apr 2019target 2023
Bear Bin Solar
Solar
150 MWIn study Terrell, GASoutheast Oct 20192023
Limestone Solar
Solar + storage
150 MWIn study Macon, GASoutheast May 20192021
Plano Skies Energy Center
Solar · Plano Skies Energy Center, LLC
150 MWIn study Kendall, ILPJM Mar 2019target 2022
Solar project GEN-2019-054, Barton County
Solar
150 MWPaused / redesign Barton, KSSPP May 2019target 2029
Dawson Solar
Solar
150 MWIn study Terrell, GASoutheast Sep 20192022
Enclave Solar Energy Center
Solar
149 MWPaused / redesign Sussex, VAPJM Jan 2019target 2027
Prattsburgh Wind Farm
Onshore wind · Prattsburgh Wind, LLC
147 MWIn study Steuben, NYNYISO Feb 2019target 2027
Kensington Solar
Solar
145 MWPaused / redesign Columbiana, OHPJM Mar 2019target 2026
Greens Bayou Expansion
Gas
140 MWPaused / redesign Harris, TXERCOT Apr 2019
Oxbow Hill Solar
Solar · Oxbow Hill Solar, LLC
140 MWIn study Madison, NYNYISO Mar 2019target 2026
Pecan Prairie South
Solar · ConnectGen Operating LLC
131 MWIn study Leon, TXERCOT Aug 2019target 2027
LA130S Project
Solar + storage
130 MWIn study Luna, NMWest Mar 2019target 2026
Solar + storage project IA-PNM-2019-08, Mckinley County
Solar + storage · RWE Solar Dev
125 MWPaused / redesign Mckinley, NMWest Apr 2019target 2022
Sugar Maple Solar
Solar · Sugar Maple Solar, LLC
125 MWIn study Lewis, NYNYISO Dec 2019target 2027
NY38 Solar
Solar · Greens Corners Solar LLC
120 MWIn study Jefferson, NYNYISO May 2019target 2026
Shorebird Solar
Solar
117 MWPaused / redesign Crawford, PAPJM Mar 2019target 2025
Trinidad ESS Addition
Battery storage
110 MWPaused / redesign Henderson, TXERCOT Dec 2019target 2026
Holtsville 138kV Energy Storage
Battery storage · Holtsville Energy Storage, LLC
110 MWIn study Suffolk, NYNYISO Dec 2019target 2026
Replace 103.1 MW of Heskett Units 1 & 2 with One (1) General Electric synchronous combustion turbine; Heskett 1 & 2
Gas
103 MWIn study Morton, NDMISO Jun 20192024
Holstein 2 Energy Storage
Solar + storage · 229HD 8me LLC
102 MWIn study Nolan, TXERCOT Aug 2019target 2027
San Bernard Solar II
Solar · San Bernard Solar II, LLC
102 MWPaused / redesign Wharton, TXERCOT Mar 2019target 2022
Jayhawk Solar
Solar · Renewable Energy Ventures, LLC
102 MWIn study Mitchell, TXERCOT Aug 2019target 2025
San Bernard Storage
Other · San Bernard Storage, LLC
101 MWPaused / redesign Wharton, TXERCOT Nov 2019target 2022
Coleto Creek ESS Addition
Battery storage
100 MWPaused / redesign Goliad, TXERCOT Dec 2019
Independence Trail Storage
Battery storage · KCE TX 16, LLC
100 MWIn study Childress, TXERCOT Dec 2019target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)