🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Oregon

SOLAR · WEST

Solar project G0625, Morrow County

Solar project G0625, Morrow County is a 191 MW solar request in interconnection study in the West interconnection queue, in Morrow County, Oregon.

Queue statusIn planning
  1. PlanningQueued Jun 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2020 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G0625
Grid region
West (non-ISO utilities)
Connection point (POI)
BPA's McNary Substation
Location
Morrow County, Oregon
Technology
Solar: 191 MW
Total requested
191 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
5 June 2019
Proposed online date
December 2020

Location

Marker shows the centre of Morrow County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Morrow County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem