SOLAR · NYISOHemlock Ridge Solar
Hemlock Ridge Solar is a 200 MW solar request in interconnection study in the NYISO interconnection queue, in Orleans County, New York, connecting to NM-NG.
Queue statusIn planning
- PlanningQueued Nov 2019 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 950
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- Hemlock Ridge Solar LLC
- Connection point (POI)
- Lockport - Mortimer 115kV
- Location
- Orleans County, New York
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Study phase
- SRIS, FS
- Queue status
- Active
- Entered queue
- 21 November 2019
- Proposed online date
- April 2028
Location
Marker shows the centre of Orleans County; the queue data does not give exact sites.
Other requests in Orleans County
- Garnet Solar and StorageSolar · 174 MW · withdrawn
- Orleans WindOnshore wind · 120 MW · withdrawn
- Barre Wind FarmOnshore wind · 120 MW · withdrawn
- Medina SolarSolar · 100 MW · withdrawn
- Farwell SolarSolar · 20.0 MW · withdrawn
- Holley Road SolarSolar · 19.9 MW · withdrawn
- Oak Orchard SolarSolar · 5.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem