| Project | Capacity | Status |
|---|---|---|
| Tolivar Power Plant (TEF- Due Diligence) Gas ยท Pecos Power Plant, LLC |
225 MW | Agreement signed |
| Two Barbaras BESS Battery storage ยท Two Barbaras BESS |
217 MW | Agreement signed |
| Sorghum BESS Battery storage ยท Blue Creek BESS, LLC |
209 MW | Agreement signed |
| Gusty Windpower Onshore wind ยท Gusty Windpower, LLC |
209 MW | Agreement signed |
| Liatris Flexible Gas Gas ยท Stone Creek Peaker LLC |
205 MW | Agreement signed |
| Dan Kearney BESS Battery storage ยท Dan Kearney BESS LLC |
204 MW | Agreement signed |
| Brookview Road BESS Battery storage ยท Brookview Reliability Project LLC |
203 MW | Agreement signed |
| Bigway Solar I Solar ยท NextEra Energy Interconnection Holdings, LLC |
203 MW | Agreement signed |
| Trenno BESS Battery storage ยท JSB1, LLC |
203 MW | Agreement signed |
| Corvus Solar Solar ยท Corvus Solar, LLC |
202 MW | Agreement signed |
| Padua Grid BESS Unit 3 Battery storage ยท Padua Grid 3, LLC |
201 MW | Agreement signed |
| Big Rooter East Storage Solar + storage ยท Big Rooter East, LLC |
201 MW | Agreement signed |
| Abeja Solar Farm Solar ยท Abeja Solar Farm LLC |
201 MW | Agreement signed |
| Resaca Oasis Storage Battery storage ยท Resaca Oasis Storage, LLC |
201 MW | Agreement signed |
| Solar project IC-1266, Bullock County Solar |
200 MW | Agreement signed |
| Battery storage project GEN-2024-SR11, Garfield County Battery storage |
200 MW | Agreement signed |
| Co200B Battery storage |
200 MW | Agreement signed |
| Solar + storage project IC-1265, Laurens County Solar + storage |
200 MW | Agreement signed |
| Bullring Wind 3 Onshore wind ยท Halcon Wind, LLC |
190 MW | Agreement signed |
| Solar project IC-1225, Baldwin County Solar |
180 MW | Agreement signed |
| Battery storage project GEN-2024-SR5, Creek County Battery storage |
177 MW | Agreement signed |
| Honey Mesquite Wind Farm Onshore wind ยท Honey Mesquite Wind Farm , LLC |
174 MW | Agreement signed |
| Fagus Solar Park 3 SLF Solar + storage ยท Greenalia Solar Power Misae III, LLC |
170 MW | Agreement signed |
| Buffalo Gap 3 Wind Repower Onshore wind ยท Buffalo Gap Wind Farm 3, LLC |
169 MW | Agreement signed |
| Onshore wind project GI-TC-2024-11, Kit Carson County Onshore wind |
167 MW | Agreement signed |
| Fagus Solar Park 2 SLF Solar + storage ยท Excel Advantage Services, LLC dba Misae Solar Park II |
167 MW | Agreement signed |
| Bocanova Power II Battery storage ยท Bocanova Power II LLC |
151 MW | Agreement signed |
| Solar + storage project IC-1276, Mitchell County Solar + storage |
150 MW | Agreement signed |
| Sf150SB Solar + storage |
150 MW | Agreement signed |
| Cannibal Draw Solar Solar + storage ยท Cannibal Draw Solar, LLC |
150 MW | Agreement signed |
| Spindletop Storage Solar + storage ยท Banita Creek Solar LLC |
143 MW | Agreement signed |
| Giga Texas Data Center Battery storage ยท Giga Texas Energy, LLC |
133 MW | Agreement signed |
| Millers Branch Solar III Solar ยท Miller's Branch Solar LLC |
133 MW | Agreement signed |
| Alamo City BESS Battery storage ยท ALAMO CITY ESS LLC |
128 MW | Agreement signed |
| Forest Creek Wind Repower Onshore wind ยท Forest Creek Wind Farm, LLC |
125 MW | Agreement signed |
| Rock Island Generating (TEF -Due Diligence) Gas ยท Kerrville Public Utility Board Public Facility Corporation |
122 MW | Agreement signed |
| Pepper Solar Farm Solar ยท Pepper Solar Farm LLC |
121 MW | Agreement signed |
| Pamela Heights I Battery storage ยท Pamela heights I Energy Center LLC |
102 MW | Agreement signed |
| Lucky 7 Solar Solar ยท Lucky 7 Solar Farm LLC |
102 MW | Agreement signed |
| Megamouth Energy Storage Battery storage ยท GCI Megamouth, LLC |
101 MW | Agreement signed |
| Battery storage project GI-TC-2024-19, Montrose County Battery storage |
100 MW | Agreement signed |
| Ne100B Battery storage |
100 MW | Agreement signed |
| Ne100S Solar |
100 MW | Agreement signed |
| AN100S Solar |
100 MW | Agreement signed |
| Cannibal Draw Storage Solar + storage ยท Cannibal Draw Solar, LLC |
98.6 MW | Agreement signed |
| Gas project LGE-GIS-2024-006, Jefferson County Gas |
94.0 MW | Agreement signed |
| Solar project IC-1224, Baldwin County Solar |
80.0 MW | Agreement signed |
| Gas project LGE-GIS-2024-002, Hopkins County Gas |
75.0 MW | Agreement signed |
| Battery storage project GEN-2024-SR2, Franklin County Battery storage |
72.5 MW | Agreement signed |
| Battery storage project GEN-2024-SR3, Lincoln County Battery storage |
72.5 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)70 ยท 16.8 GW
- Southeast (non-ISO utilities)23 ยท 9,901 MW
- West (non-ISO utilities)16 ยท 1,964 MW
- SPP (Southwest Power Pool)8 ยท 1,671 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)