United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTBocanova Power II
Bocanova Power II is a 151 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Brazoria County, Texas.
Queue statusConsented
- PlanningQueued Oct 2024 (completed)
- ConsentedAug 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 25INR0706
- Grid region
- ERCOT (Texas)
- Developer
- Bocanova Power II LLC
- Connection point (POI)
- 39030 TNMP Alvin 138kV
- Location
- Brazoria County, Texas
- Technology
- Battery: 151 MW
- Total requested
- 151 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 10 October 2024
- Agreement signed
- 19 August 2025
- Proposed online date
- June 2026
Location
Marker shows the centre of Brazoria County; the queue data does not give exact sites.
Other requests in Brazoria County
- Austin Bayou SolarSolar + storage · 503 MW · agreement signed
- Gamay Energy StorageBattery storage · 419 MW · agreement signed
- Aldrin 345 BESSBattery storage · 362 MW · agreement signed
- Cottonwood Bayou SolarSolar · 351 MW · agreement signed
- Myrtle SolarSolar · 321 MW · agreement signed
- Elio BESSBattery storage · 317 MW · agreement signed
- First Capitol BESSBattery storage · 258 MW · agreement signed
- Hastings Park BESSBattery storage · 256 MW · agreement signed
- Clutch City Solar Phase IISolar · 251 MW · agreement signed
- Tanglewood SolarSolar · 251 MW · agreement signed
- Aldrin 138 BESSBattery storage · 207 MW · agreement signed
- Desna BESSBattery storage · 206 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem