United States › Grid › Interconnection queues › Wisconsin

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Wisconsin — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24049.1 GW
Active in queue26.6 GW117 requests
Agreement signed3,635 MW26 requests
Withdrawn24049.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

240 requests · page 2 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Coal project G553, Columbia County
Coal
280 MWWithdrawn / abandoned Columbia, WIMISO Sep 2005target 2007
Coal project G527, Grant County
Coal
280 MWWithdrawn / abandoned Grant, WIMISO Jun 2005target 2006
Other project G001, Brown County
Other
255 MWWithdrawn / abandoned Brown, WIMISO Nov 1995target 2014
Other project G139, Grant County
Other
250 MWWithdrawn / abandoned Grant, WIMISO Oct 2001target 2004
Onshore wind project J135, Buffalo County
Onshore wind
200 MWWithdrawn / abandoned Buffalo, WIMISO Feb 2008target 2011
Battery storage project J4192, Racine County
Battery storage
200 MWWithdrawn / abandoned Racine, WIMISO Oct 2025target 2029
Solar project J1474, Chippewa County
Solar
200 MWWithdrawn / abandoned Chippewa, WIMISO Apr 2019target 2025
Solar project J1705, Columbia County
Solar
200 MWWithdrawn / abandoned Columbia, WIMISO Jun 2020target 2024
Battery storage project J1884, Columbia County
Battery storage
200 MWWithdrawn / abandoned Columbia, WIMISO Aug 2021target 2024
Onshore wind project J1366, Eau Claire County
Onshore wind
200 MWWithdrawn / abandoned Eau Claire, WIMISO Apr 2019target 2022
Other project G087, Grant County
Other
200 MWWithdrawn / abandoned Grant, WIMISO Mar 2001
Battery storage project J2211, Brown County
Battery storage
200 MWWithdrawn / abandoned Brown, WIMISO Sep 2024target 2024
Onshore wind project J094, Manitowoc County
Onshore wind
200 MWWithdrawn / abandoned Manitowoc, WIMISO Nov 2011target 2010
Onshore wind project J139, Grant County
Onshore wind
200 MWWithdrawn / abandoned Grant, WIMISO Oct 2009
Solar project J2148, Outagamie County
Solar
200 MWWithdrawn / abandoned Outagamie, WIMISO Oct 2021target 2028
Solar project J1044, Walworth County
Solar
200 MWWithdrawn / abandoned Walworth, WIMISO Mar 2018target 2022
Solar project J2271, Columbia County
Solar
200 MWWithdrawn / abandoned Columbia, WIMISO Jul 2021target 2025
Battery storage project J2335, Portage County
Battery storage
200 MWWithdrawn / abandoned Portage, WIMISO Sep 2022target 2025
Onshore wind project J1631, Clark County
Onshore wind
200 MWWithdrawn / abandoned Clark, WIMISO Jun 2020target 2023
Solar project J1121, Marathon County
Solar
200 MWWithdrawn / abandoned Marathon, WIMISO Mar 2018target 2021
Solar project J1047, Walworth County
Solar
200 MWWithdrawn / abandoned Walworth, WIMISO Mar 2018target 2022
Solar project J1042, Walworth County
Solar
200 MWWithdrawn / abandoned Walworth, WIMISO Mar 2018target 2023
Onshore wind project J712, Iowa County
Onshore wind
200 MWWithdrawn / abandoned Iowa, WIMISO Sep 2016target 2020
Other project G306, Dodge County
Other
200 MWWithdrawn / abandoned Dodge, WIMISO Mar 2003target 2004
Solar project J2018, Clark County
Solar
190 MWWithdrawn / abandoned Clark, WIMISO Nov 2021target 2026
Gas project G268, Wood County
Gas
189 MWWithdrawn / abandoned Wood, WIMISO Nov 2002target 2005
Other project G302, Green Lake County
Other
160 MWWithdrawn / abandoned Green Lake, WIMISO Feb 2003target 2003
Solar project J1582, St. Croix County
Solar
160 MWWithdrawn / abandoned St. Croix, WIMISO Feb 2022target 2024
Onshore wind project G376, Green Lake County
Onshore wind
160 MWWithdrawn / abandoned Green Lake, WIMISO Nov 2003target 2006
Onshore wind project G335, Fond Du Lac County
Onshore wind
160 MWWithdrawn / abandoned Fond Du Lac, WIMISO Apr 2003target 2005
Solar project J2366, Portage County
Solar
160 MWWithdrawn / abandoned Portage, WIMISO Sep 2022target 2030
Onshore wind project J134, Dane County
Onshore wind
150 MWWithdrawn / abandoned Dane, WIMISO May 2010target 2013
Onshore wind project J600, Rock County
Onshore wind
150 MWWithdrawn / abandoned Rock, WIMISO May 2016target 2018
Solar project J1567, Outagamie County
Solar
150 MWWithdrawn / abandoned Outagamie, WIMISO Feb 2022target 2023
Solar project J3912, Chippewa County
Solar
150 MWWithdrawn / abandoned Chippewa, WIMISO Feb 2025target 2030
Onshore wind project J2345, Marathon County
Onshore wind
150 MWWithdrawn / abandoned Marathon, WIMISO Sep 2022target 2028
Battery storage project J2218, Manitowoc County
Battery storage
150 MWWithdrawn / abandoned Manitowoc, WIMISO Aug 2021target 2024
Solar project J1938, Portage County
Solar
150 MWWithdrawn / abandoned Portage, WIMISO Nov 2021target 2026
Solar project J1775, Calumet County
Solar
150 MWWithdrawn / abandoned Calumet, WIMISO Jun 2020target 2023
Onshore wind project J606, Monroe County
Onshore wind
150 MWWithdrawn / abandoned Monroe, WIMISO May 2016target 2018
Onshore wind project G773, Brown County
Onshore wind
150 MWWithdrawn / abandoned Brown, WIMISO Mar 2007target 2010
Battery storage project J2102, Buffalo County
Battery storage
150 MWWithdrawn / abandoned Buffalo, WIMISO Aug 2021target 2024
Solar project J1945, Portage County
Solar
150 MWWithdrawn / abandoned Portage, WIMISO Nov 2021target 2026
Onshore wind project J3332, Calumet County
Onshore wind
150 MWWithdrawn / abandoned Calumet, WIMISO Apr 2024target 2028
Onshore wind project J738, Green County
Onshore wind
150 MWWithdrawn / abandoned Green, WIMISO Nov 2016target 2020
Solar project J3927, Sheboygan County
Solar
150 MWWithdrawn / abandoned Sheboygan, WIMISO Feb 2025target 2028
Solar project J3476, St. Croix County
Solar
150 MWWithdrawn / abandoned St. Croix, WIMISO Apr 2024target 2028
Onshore wind project G281, Green County
Onshore wind
130 MWWithdrawn / abandoned Green, WIMISO Nov 2003target 2005
Onshore wind project G570, Kewaunee County
Onshore wind
125 MWWithdrawn / abandoned Kewaunee, WIMISO Nov 2005target 2011
Battery storage project J2416, Trempealeau County
Battery storage
125 MWWithdrawn / abandoned Trempealeau, WIMISO Sep 2022target 2027

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)