SOLAR Β· MISOSolar project J1474, Chippewa County
Solar project J1474, Chippewa County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Chippewa County, Wisconsin, connecting to NORTHERN STATES POWER COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- ConsentedJan 2023 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1474
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN STATES POWER COMPANY
- Connection point (POI)
- Pine Lake - Eagle Point 115kV Line
- Location
- Chippewa County, Wisconsin
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 29 April 2019
- Agreement signed
- 26 January 2023
- Proposed online date
- July 2025
- Withdrawn
- November 2023
Location
Marker shows the centre of Chippewa County; the queue data does not give exact sites.