United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Texas (2023 requests) — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown36979.0 GW
Active in queue79.0 GW369 requests
Agreement signed25.0 GW108 requests
Withdrawn11324.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

369 requests · page 2 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Bulldog Power (TEF - Due Diligence)
Gas · Bulldog Power LLC
311 MWIn study Brazoria, TXERCOT Nov 2023target 2027
Oak Tree Energy Storage
Battery storage · Live Oak Energy Storage, LLC
310 MWIn study Lavaca, TXERCOT Dec 2023target 2029
Buffalo Prairie Storage
Solar + storage · Buffalo Meadow Energy Center, LLC
308 MWIn study Robertson, TXERCOT Jan 2023target 2028
Haute Stockage
Battery storage
307 MWPaused / redesign Shackelford, TXERCOT Oct 2023target 2027
Beaujolais BESS
Battery storage
307 MWPaused / redesign Lamar, TXERCOT Dec 2023target 2026
Cuchillas BESS
Solar + storage · Gransolar Texas Two
307 MWIn study Webb, TXERCOT Sep 2023target 2028
Laurel Wind Energy Center
Onshore wind · LAUREL ENERGY CENTER, LLC
307 MWAgreement signed Pecos, TXERCOT Jun 2023target 2027
Wolf Hollow III
Gas · Wolf Hollow II Power LLC
306 MWIn study Hood, TXERCOT Jun 2023target 2027
Panhandle Flagship Solar 2
Solar + storage · Panhandle Solar Group Operating Company LLC
304 MWAgreement signed Hutchinson, TXERCOT Mar 2023target 2027
WOE Gyp King Wind
Onshore wind · KSK Wind Farm 1, LLC
304 MWPaused / redesign King, TXERCOT Apr 2023target 2029
NavBoot BESS
Battery storage · Navboot BESS LLC
304 MWAgreement signed Nueces, TXERCOT Mar 2023target 2026
Whitewright Solar 2
Solar · SunWR, LLC
302 MWIn study Grayson, TXERCOT Dec 2023target 2028
Amerada Solar
Solar + storage · Amerada Solar, LLC
302 MWIn study Freestone, TXERCOT May 2023target 2028
Riverbend Solar SLF
Solar + storage · Riverbend Renewables, LLC
302 MWIn study Falls, TXERCOT Mar 2023target 2027
Rubicon Power BESS
Battery storage · Rubicon Power LLC
301 MWIn study Brazoria, TXERCOT Nov 2023target 2026
Acker BESS
Battery storage · Ogallala BESS LLC
301 MWAgreement signed Castro, TXERCOT Jun 2023target 2028
Battery storage project GEN-2022-139, Harrison County
Battery storage
300 MWIn study Harrison, TXSPP Feb 2023target 2030
Tres Rios Ranch BESS
Solar + storage · LectricWind LLC
290 MWIn study Upton, TXERCOT May 2023target 2027
Inadale BESS
Solar + storage · Inadale BESS, LLC
287 MWIn study Scurry, TXERCOT Feb 2023target 2028
Inadale Solar
Solar + storage · Inadale Solar, LLC
281 MWIn study Scurry, TXERCOT Feb 2023target 2028
Santa Garcias Solar
Solar · Oxy Renewable Energy LLC
265 MWIn study Kleberg, TXERCOT Jun 2023target 2028
Dundee East B Wind
Onshore wind · Felix 2, LLC
261 MWAgreement signed Baylor, TXERCOT Jan 2023target 2027
Panhandle Flagship Solar 3
Solar + storage · Panhandle Solar Group Operating Company LLC
260 MWAgreement signed Hutchinson, TXERCOT Mar 2023target 2027
Ochoa Energy Storage
Battery storage · Ochoa Energy Storage LLC
260 MWIn study Waller, TXERCOT Apr 2023target 2027
Goodnight Wind II
Onshore wind · FGE Goodnight II, LLC
259 MWAgreement signed Armstrong, TXERCOT Apr 2023target 2027
First Capitol BESS
Battery storage · First Capitol BESS, LLC
258 MWAgreement signed Brazoria, TXERCOT Oct 2023target 2027
Van Zandt Energy Storage
Battery storage · Rocky Mountain Energy Holdings, LLC
257 MWIn study Ector, TXERCOT Jun 2023target 2027
Shamrock II Wind
Onshore wind
257 MWPaused / redesign Crockett, TXERCOT Jul 2023target 2028
Nautilus Heavy Storage
Battery storage · Nautilus Heavy Storage, LLC
256 MWIn study San Patricio, TXERCOT Dec 2023target 2028
Leaning Tree BESS
Battery storage
256 MWPaused / redesign Throckmorton, TXERCOT Nov 2023target 2026
Lonesome Dove BESS
Battery storage
256 MWPaused / redesign Throckmorton, TXERCOT Nov 2023target 2026
Railway BESS
Battery storage
255 MWPaused / redesign Rusk, TXERCOT Jan 2023target 2026
Staked Plains BESS
Battery storage
255 MWPaused / redesign Lubbock, TXERCOT Mar 2023target 2026
Lazy U Solar 2
Solar · Lazy U Solar 2
252 MWIn study Hardeman, TXERCOT Aug 2023target 2029
Little Ridge Storage
Battery storage · TX BESS B LLC
252 MWIn study Collin, TXERCOT May 2023target 2025
Lazy U Solar 1
Solar · Lazy U Solar 1
252 MWIn study Hardeman, TXERCOT Aug 2023target 2029
Juniper Ridge BESS 2
Battery storage · Lazy U ESS 2
252 MWIn study Hardeman, TXERCOT Aug 2023target 2029
Juniper Ridge BESS 1
Battery storage · Lazy U ESS 1
252 MWIn study Hardeman, TXERCOT Sep 2023target 2029
Buffalo Meadow Solar
Solar + storage · Buffalo Meadow Energy Center, LLC
251 MWIn study Robertson, TXERCOT Feb 2023target 2028
Mesa View Storage
Battery storage · Mesa View Storage, LLC
251 MWIn study Upton, TXERCOT Apr 2023target 2027
Clutch City Solar Phase II
Solar · HZ SOLAR I, LLC
251 MWAgreement signed Brazoria, TXERCOT Feb 2023target 2028
Fort Concho Energy storage
Battery storage · Rocky Mountain Energy Development, LLC
251 MWIn study Tom Green, TXERCOT Jan 2023target 2028
Bluegill BESS
Battery storage · Bluegill BESS, LLC
251 MWIn study Harris, TXERCOT Jun 2023target 2027
Sf250SB
Solar + storage
250 MWAgreement signed Hudspeth, TXWest Sep 2023target 2028
Misty Hollow BESS
Battery storage · Clear Fork BESS, LLC
246 MWAgreement signed Grimes, TXERCOT Dec 2023target 2028
Hill Valley BESS
Battery storage · Hill Valley BESS, LLC
246 MWIn study Grimes, TXERCOT Dec 2023target 2028
Diaz BESS
Battery storage · BRP Blue Topaz 10, LLC
242 MWIn study Cameron, TXERCOT May 2023target 2027
Duffy BESS
Solar + storage · Duffy Energy Storage LLC
241 MWAgreement signed Matagorda, TXERCOT Aug 2023target 2026
Jane Storage Energy Center
Battery storage · NMRE Holdings, LLC
241 MWIn study Martin, TXERCOT Sep 2023target 2027
GridGuardian BESS
Battery storage · SMT Temple BESS LLC
228 MWIn study Bell, TXERCOT Sep 2023target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)