Sf250SB

Sf250SB is a 250 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Hudspeth County, Texas, connecting to El Paso Electric Company.

Queue statusConsented
  1. PlanningQueued Sep 2023 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
LG-23-9-4
Grid region
West (non-ISO utilities)
Utility / transmission owner
El Paso Electric Company
Connection point (POI)
San Felipe 115kV Substation
Location
Hudspeth County, Texas
Technology
Solar: 250 MW · Battery
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
LGIA EXECUTED
Queue status
Active
Entered queue
29 September 2023
Proposed online date
December 2028

Location

Marker shows the centre of Hudspeth County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Hudspeth County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem