ONSHORE WIND · WESTGranite Mountain Wind Power (Duke Energy Generation Services)
Granite Mountain Wind Power (Duke Energy Generation Services) is a 101 MW onshore wind request withdrawn in the West interconnection queue, in Hudspeth County, Texas, connecting to El Paso Electric Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2010 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 34
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- El Paso Electric Company
- Connection point (POI)
- Coyote-RGDC 115 kV line @ point of EPE ownership
- Location
- Hudspeth County, Texas
- Technology
- Wind: 101 MW
- Total requested
- 101 MW
- Service type
- NRIS and ERIS
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 20 August 2010
- Proposed online date
- December 2012
Location
Marker shows the centre of Hudspeth County; the queue data does not give exact sites.
Other requests in Hudspeth County