Requests shown9821.1 GW
Active in queue23.9 GW123 requests
Agreement signed1,860 MW18 requests
Withdrawn29566.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

98 requests · page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J4173, Wapello County
Battery storage
199 MWIn study Wapello, IAMISO Oct 2025target 2028
Battery storage project J4155, Linn County
Battery storage
195 MWIn study Linn, IAMISO Oct 2025target 2029
Onshore wind project J3702, Mitchell County
Onshore wind
180 MWIn study Mitchell, IAMISO Mar 2024target 2028
Onshore wind project J2988, Humboldt County
Onshore wind
175 MWIn study Humboldt, IAMISO Sep 2022target 2025
Onshore wind project J3926, Webster County
Onshore wind
170 MWIn study Webster, IAMISO Mar 2025target 2030
Battery storage project J2653, Polk County
Battery storage
170 MWIn study Polk, IAMISO Sep 2022target 2027
Battery storage project J2655, Polk County
Battery storage
170 MWIn study Polk, IAMISO Sep 2022target 2026
Onshore wind project J1365, Tama County
Onshore wind
169 MWIn study Tama, IAMISO Apr 2019target 2024
Onshore wind project J2576, Louisa County
Onshore wind
164 MWIn study Louisa, IAMISO Sep 2022target 2025
Solar project J2757, Cherokee County
Solar
160 MWIn study Cherokee, IAMISO Oct 2025target 2026
Gas project J2946, Dubuque County
Gas
160 MWIn study Dubuque, IAMISO Sep 2022target 2027
Gas project J3154, Franklin County
Gas
160 MWIn study Franklin, IAMISO Sep 2022target 2027
Gas project J3153, Clinton County
Gas
160 MWIn study Clinton, IAMISO Sep 2022target 2027
Solar project J3137, Pocahontas County
Solar
156 MWIn study Pocahontas, IAMISO Oct 2025target 2026
Solar project J3461, Muscatine County
Solar
156 MWIn study Muscatine, IAMISO Apr 2024target 2028
Onshore wind project J3898, Howard County
Onshore wind
155 MWIn study Howard, IAMISO Feb 2025target 2030
Onshore wind project J2686, Muscatine County
Onshore wind
150 MWIn study Muscatine, IAMISO Sep 2022target 2026
Replacing 150 MW of coal generation with BESS at Lansing; Lansing 4
Battery storage
150 MWIn study Allamakee, IAMISO Apr 2025target 2026
Solar project J3107, Johnson County
Solar
150 MWIn study Johnson, IAMISO Oct 2025target 2025
Replacing 130 MW of coal generation with BESS at Lansing; Lansing 4
Battery storage
130 MWIn study Allamakee, IAMISO Apr 2025target 2026
Surplus; J1734
Other
120 MWIn study Lee, IAMISO Nov 2024target 2025
Solar project J4086, Wapello County
Solar
120 MWIn study Wapello, IAMISO Oct 2025target 2029
Onshore wind project J1769, Howard County
Onshore wind
120 MWIn study Howard, IAMISO Jun 2020target 2026
Battery storage project J3159, Dubuque County
Battery storage
100 MWIn study Dubuque, IAMISO Sep 2022target 2027
Replacing 100 MW of Solar with Nuclear; Duane Arnold
Nuclear
100 MWIn study Linn, IAMISO Aug 2025target 2029
Battery storage project J2949, Marshall County
Battery storage
100 MWIn study Marshall, IAMISO Sep 2022target 2027
Solar project J4037, Franklin County
Solar
100 MWIn study Franklin, IAMISO Jun 2025target 2030
Battery storage project J3158, Cerro Gordo County
Battery storage
100 MWIn study Cerro Gordo, IAMISO Sep 2022target 2027
Onshore wind project J2031, Tama County
Onshore wind
100 MWIn study Tama, IAMISO Aug 2021target 2026
Battery storage project J2066, Henry County
Battery storage
100 MWIn study Henry, IAMISO Aug 2021target 2022
Battery storage project J2120, Linn County
Battery storage
100 MWIn study Linn, IAMISO Aug 2021target 2025
Battery storage project J4172, Wapello County
Battery storage
99.0 MWIn study Wapello, IAMISO Oct 2025target 2028
Gas project J4145, Cerro Gordo County
Gas
98.0 MWIn study Cerro Gordo, IAMISO Oct 2025target 2028
Gas project J1359, Linn County
Gas
95.0 MWIn study Linn, IAMISO Apr 2019target 2025
Surplus; Old Gold
Other
80.0 MWIn study Worth, IAMISO Jun 2024target 2029
Gas project J2948, Marshall County
Gas
75.0 MWIn study Marshall, IAMISO Sep 2022target 2024
Surplus; J495
Battery storage
75.0 MWIn study Kossuth, IAMISO Jul 2025target 2026
Onshore wind project J1998, Franklin County
Onshore wind
66.0 MWIn study Franklin, IAMISO Aug 2021target 2024
Replacing 50 MW of Solar with Nuclear; Duane Arnold
Nuclear
64.0 MWIn study Linn, IAMISO Aug 2025target 2029
Solar project J1889, Linn County
Solar
60.0 MWIn study Linn, IAMISO Aug 2021target 2025
Solar project J1529, Carroll County
Solar
50.0 MWIn study Carroll, IAMISO Apr 2021target 2026
Solar + storage project J2951, Union County
Solar + storage
50.0 MWIn study Union, IAMISO Sep 2022target 2024
Solar project J1530, Mills County
Solar
50.0 MWIn study Mills, IAMISO Apr 2021target 2026
Solar project J1532, Page County
Solar
50.0 MWIn study Page, IAMISO Apr 2021target 2026
Solar project J4150, Cass County
Solar
42.2 MWIn study Cass, IAMISO Oct 2025target 2027
Surplus; J1132
Other
40.0 MWIn study Union, IAMISO target 2025
Onshore wind project J2122, Franklin County
Onshore wind
33.0 MWIn study Franklin, IAMISO Aug 2021target 2024
Solar project J1927, Muscatine County
Solar
23.4 MWIn study Muscatine, IAMISO Dec 2021target 2027
Page 2 of 2

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20192025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)