🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Iowa

BATTERY STORAGE · MISO

Battery storage project J2655, Polk County

Battery storage project J2655, Polk County is a 170 MW battery storage request in interconnection study in the MISO interconnection queue, in Polk County, Iowa, connecting to MIDAMERICAN ENERGY CO..

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2655
Grid region
MISO (Midcontinent)
Utility / transmission owner
MIDAMERICAN ENERGY CO.
Connection point (POI)
Army Post 161 kV Substation
Location
Polk County, Iowa
Technology
Battery: 170 MW
Total requested
170 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
15 September 2022
Proposed online date
May 2026

Location

Marker shows the centre of Polk County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Polk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem