🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Iowa

ONSHORE WIND · MISO

Onshore wind project J1998, Franklin County

Onshore wind project J1998, Franklin County is a 66.0 MW onshore wind request in interconnection study in the MISO interconnection queue, in Franklin County, Iowa, connecting to ITC MIDWEST.

Queue statusIn planning
  1. PlanningQueued Aug 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1998
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC MIDWEST
Connection point (POI)
Nuthatch Switching Station
Location
Franklin County, Iowa
Technology
Wind: 66.0 MW
Total requested
66.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Active
Entered queue
4 August 2021
Proposed online date
June 2024

Location

Marker shows the centre of Franklin County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Franklin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem