United States › Grid › Interconnection queues › Iowa

SOLAR · MISO

Solar project J1532, Page County

Solar project J1532, Page County is a 50.0 MW solar request in interconnection study in the MISO interconnection queue, in Page County, Iowa, connecting to MIDAMERICAN ENERGY CO..

Queue statusIn planning
  1. PlanningQueued Apr 2021 (current stage)
  2. ConsentedAug 2024 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1532
Grid region
MISO (Midcontinent)
Utility / transmission owner
MIDAMERICAN ENERGY CO.
Connection point (POI)
Clarinda-Coburg 69 kV
Location
Page County, Iowa
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
16 April 2021
Agreement signed
5 August 2024
Proposed online date
September 2026

Location

Marker shows the centre of Page County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Page County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem