Withdrawn queue requests in ISO-NE (New England) — page 19

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown982118.1 GW
Active in queue14.6 GW72 requests
Agreement signed8,609 MW45 requests
Withdrawn982118.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

982 requests · page 19 of 20
ProjectCapacityStatusLocationRegionQueuedOnline
Kenyon Substation - NG Western RI DG Area Study
Solar
3.5 MWWithdrawn / abandoned Washington, RIISO-NE Mar 2020target 2021
Hopkins Hill - NG WRI DG Area Study #2 <5 MW
Solar
3.5 MWWithdrawn / abandoned Kent, RIISO-NE Aug 2020target 2022
Falmouth 933 - EMA ASO
Solar + storage
3.5 MWWithdrawn / abandoned Barnstable, MAISO-NE Jun 2022target 2023
Bath 115 kV SS - Midcoast Area DG Study
Solar
3.4 MWWithdrawn / abandoned Lincoln, MEISO-NE Oct 2023target 2024
Hydro
Hydro
3.3 MWWithdrawn / abandoned Hampden, MAISO-NE Jul 2009target 2014
Solar + battery
Solar + storage
3.2 MWWithdrawn / abandoned Barnstable, MAISO-NE Apr 2020target 2023
Tower Hill - NG WRI DG Area Study #2 <5 MW
Solar
3.1 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2020target 2025
Tower Hill Substation - Western RI DER Study #3
Solar
3.1 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2024target 2026
Solar
Solar
3.1 MWWithdrawn / abandoned Worcester, MAISO-NE Dec 2015target 2017
Paxton BESS
Battery storage
3.0 MWWithdrawn / abandoned Worcester, MAISO-NE Jul 2024target 2024
Point St Substation – Aldrich St BESS
Battery storage
3.0 MWWithdrawn / abandoned Providence, RIISO-NE Nov 2024target 2026
Sheld BESS
Battery storage
3.0 MWWithdrawn / abandoned Hampden, MAISO-NE Aug 2024target 2025
Battery Storage
Battery storage
3.0 MWWithdrawn / abandoned Worcester, MAISO-NE Aug 2024target 2025
Fisher Road 657 - EMA ASO
Solar + storage
3.0 MWWithdrawn / abandoned Bristol, MAISO-NE Jun 2022target 2023
Solar + Battery Storage
Solar + storage
3.0 MWWithdrawn / abandoned Hampshire, MAISO-NE Apr 2021target 2021
Putnam Pike - NG WRI DG Area Study #2 <5 MW
Solar
3.0 MWWithdrawn / abandoned Providence, RIISO-NE Aug 2020target 2021
Solar plus Battery
Solar + storage
3.0 MWWithdrawn / abandoned Hampshire, MAISO-NE Feb 2022target 2022
TMLP Landfill Solar
Solar
3.0 MWWithdrawn / abandoned Bristol, MAISO-NE Jul 2024target 2025
New London Substation - NG Western RI DG Area Study
Solar
3.0 MWWithdrawn / abandoned Kent, RIISO-NE Mar 2020target 2021
Coopers Mills 115 kV SS - Midcoast Area DG Study
Solar
2.9 MWWithdrawn / abandoned Lincoln, MEISO-NE Oct 2023target 2024
Wind uprate
Onshore wind
2.9 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2015target 2018
Solar
Solar
2.8 MWWithdrawn / abandoned Plymouth, MAISO-NE Apr 2020target 2023
Solar plus Battery
Solar + storage
2.8 MWWithdrawn / abandoned Hampden, MAISO-NE May 2022target 2023
EE 2024 SEMA/Cape ASO Group Study
Solar + storage
2.8 MWWithdrawn / abandoned Barnstable, MAISO-NE May 2024target 2026
Solar
Solar
2.7 MWWithdrawn / abandoned Worcester, MAISO-NE Dec 2015target 2017
Wind
Onshore wind
2.7 MWWithdrawn / abandoned Coos, NHISO-NE Mar 2012target 2012
Puddledock Road 115 kV SS - Augusta Area Study
Solar
2.5 MWWithdrawn / abandoned Kennebec, MEISO-NE Oct 2020target 2023
Oswald - WMA ASO
Solar + storage
2.5 MWWithdrawn / abandoned Franklin, MAISO-NE Jan 2022target 2023
Solar
Solar
2.5 MWWithdrawn / abandoned Franklin, MAISO-NE Apr 2020target 2023
Royalston - NG Western MA Area Cluster Study
Solar
2.5 MWWithdrawn / abandoned Worcester, MAISO-NE Dec 2018target 2022
Douglas Woods Wind Unit 12
Onshore wind
2.5 MWWithdrawn / abandoned Worcester, MAISO-NE May 2010target 2014
EE 2024 SEMA/Cape ASO Group Study
Solar + storage
2.5 MWWithdrawn / abandoned Barnstable, MAISO-NE May 2024target 2026
Solar + Battery Storage
Solar + storage
2.5 MWWithdrawn / abandoned Bristol, MAISO-NE Apr 2021target 2021
Solar + Battery Storage
Solar + storage
2.4 MWWithdrawn / abandoned Bristol, MAISO-NE Apr 2020target 2021
Chase Hill Substation - Western RI DER Study #3
Solar
2.4 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2024target 2026
Wolf Hill substation - NG Western RI DG Area Study
Solar
2.2 MWWithdrawn / abandoned Providence, RIISO-NE Mar 2020target 2021
Project Increase
Other
2.2 MWWithdrawn / abandoned Hartford, CTISO-NE Apr 2017target 2017
Solar
Solar
2.2 MWWithdrawn / abandoned Windham, VTISO-NE Jul 2012target 2013
Individual @ French King
Solar + storage
2.2 MWWithdrawn / abandoned Franklin, MAISO-NE Jun 2023
Generator Increase
Other
2.1 MWWithdrawn / abandoned Hartford, CTISO-NE Dec 2018target 2019
CMP Vallee Lane 115 kV SS - Louden-Biddeford Area DG Study
Solar
2.0 MWWithdrawn / abandoned Cumberland, MEISO-NE Dec 2023target 2024
Athens 115 kV SS - CMP Wyman Area Study
Solar
2.0 MWWithdrawn / abandoned Somerset, MEISO-NE Mar 2023target 2024
Solar + Battery
Solar + storage
2.0 MWWithdrawn / abandoned Plymouth, MAISO-NE Apr 2020target 2025
Pratts Junction substation - NG Western MA Area Cluster Study
Solar
2.0 MWWithdrawn / abandoned Worcester, MAISO-NE Mar 2019target 2020
Ludden Lane 115 kV SS - Sturtevant-Leeds-Livermore-Ludden-Riley Area DG Study
Solar
2.0 MWWithdrawn / abandoned Oxford, MEISO-NE Sep 2023target 2024
Topsham 115 kV SS - Midcoast Area DG Study
Solar
2.0 MWWithdrawn / abandoned Waldo, MEISO-NE Oct 2023target 2024
Individual @ Amherst
Battery storage
2.0 MWWithdrawn / abandoned Hampshire, MAISO-NE Jun 2023target 2024
Solar + Battery Storage
Solar + storage
2.0 MWWithdrawn / abandoned Berkshire, MAISO-NE May 2020target 2022
Augusta E. Side 115 kV SS - Augusta Area Study
Solar
2.0 MWWithdrawn / abandoned Kennebec, MEISO-NE Oct 2020target 2024
Highland/Park St 115 kV SS - Midcoast Area DG Study
Solar
2.0 MWWithdrawn / abandoned Knox, MEISO-NE Oct 2023target 2024
Page 19 of 20

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)