🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Massachusetts

SOLAR + STORAGE · ISO-NE

Solar plus Battery

Solar plus Battery is a 3.0 MW solar + storage request withdrawn in the ISO-NE interconnection queue, in Hampshire County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2022 (completed)
  2. Withdrawn / abandonedSep 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1229
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource 13.8kV Circuit 18G4
Location
Hampshire County, Massachusetts
Technology
Solar: 3.0 MW · Battery
Total requested
3.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
22 February 2022
Proposed online date
December 2022
Withdrawn
September 2022

Location

Marker shows the centre of Hampshire County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Hampshire County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem