SOLAR + STORAGE · ISO-NE

Solar + Battery Storage

Solar + Battery Storage is a 2.0 MW solar + storage request withdrawn in the ISO-NE interconnection queue, in Berkshire County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2020 (completed)
  2. Withdrawn / abandonedSep 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1027
Grid region
ISO-NE (New England)
Connection point (POI)
National Grid, 13.8kV, DISTRIBUTION CIRCUIT #09-1102W1
Location
Berkshire County, Massachusetts
Technology
Solar: 2.0 MW · Battery
Total requested
2.0 MW
Service type
Network resource (NRIS)
Study phase
In Progress
Queue status
Withdrawn
Entered queue
14 May 2020
Proposed online date
December 2022
Withdrawn
September 2022

Location

Marker shows the centre of Berkshire County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Berkshire County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem